2026 Delivery Schedule Template 2026-10-20.xlsx

Run 5 · uploaded Nov 02, 2026 09:03 AM by VIVA Procurement · sheet "Sheet1 (2)", 80 batches

ready
41will update in Wrike 141need review 448unmatched 69at risk 33 LA · 65 Need By 1waiting on TAKA 47no change

5 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.

Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 2 · SZXCHI63001Y · ETA to DALLAS
7 25-107 IP1
Commonwealth Charter Academy · Extrution Aluminum panel
PO 25-107-005
1 note
  • task has no Need By date
AIR 25-107 - Commonwealth
fuzzy · 84% · task title has no pack code to confirm IP1
1 candidate
none → Mar 25, 2026
TAKA: 2026-03-25 to DALLAS
Not assessed Never Needs review
8 25-107 IP2
Commonwealth Charter Academy · Extrution Aluminum panel
PO 25-107-004
1 note
  • task has no Need By date
AIR 25-107 - Commonwealth
fuzzy · 84% · task title has no pack code to confirm IP2
1 candidate
none → Mar 25, 2026
TAKA: 2026-03-25 to DALLAS
Not assessed Never Needs review
Batch 3 · SZXCHI64001Y KE320/03APR · ETA to DALLAS
21 25-213 - - Mock Up
Waxahachie ISD Creek HS Frame & BCCB · MOCK UP
PO NA
1 note
  • task has no Need By date
AIR 25-213 - Waxahachie ISD Creek HS - SAMP (EXPEDITED) - TAKA- PO APPROVAL
fuzzy · 75% · only TAKA task for job 25-213
1 candidate
none → Apr 05, 2026
TAKA: 2026-04-05 to DALLAS
Not assessed Never Needs review
Batch 5 · SZXCHI64002Y · ETA to DALLAS
55 24-120 -1IP1 replacement (part of materials)
TAMIU - MS Scope & Bridge · 5mm Aluminum panel
PO NA
2 notes
  • task has no Need By date
  • container_dispatch 2026-04-14 differs from batch majority 2026-04-11
AIR 24-120-10 - TAMIU
fuzzy · 77% · task title has no pack code to confirm 1IP1
1 candidate
none → Apr 13, 2026
TAKA: 2026-04-13 to DALLAS
Not assessed Never Needs review
Batch 6 · SZXCHI64004Y · ETA to DALLAS
59 24-120 -1IP1 replacement (Balance materials)
TAMIU - MS Scope & Bridge · 5mm Aluminum panel
PO NA
1 note
  • task has no Need By date
AIR 24-120-10 - TAMIU
fuzzy · 77% · task title has no pack code to confirm 1IP1
1 candidate
none → Apr 17, 2026
TAKA: 2026-04-17 to DALLAS
Not assessed Never Needs review
Batch 7 · SZXCHI64003Y · ETA to DALLAS
61 25-050 - -replacement Infill Pack 1 (except 2pcs )
Cheshire Elementary School
PO NA
1 note
  • task has no Need By date
AIR 25-050 - Cheshire Elementary School - Infill Pack 1 - Remake panels
fuzzy · 90% · job 25-050 + pack IP1; close runner-up
3 candidates
Apr 28, 2026 → Apr 16, 2026 -12d
TAKA: 2026-04-16 to DALLAS
Not assessed Never Needs review
Batch 9 · SZXLAX64166X · ETA to LA
100 25-142 -- MP1
QTS DFW2 DC3 · SS316 FITTINGS
PO NA
2 notes
  • task has no Need By date
  • new ETA May 21, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-142 - QTS DFW2 DC3 - MP1 - TAKA
fuzzy · 100% · job 25-142 + pack MP1
1 candidate
Aug 12, 2026 Aug 21, 2026 → May 21, 2026 -92d
TAKA: 2026-05-07 to LA
On track Never Needs review
Batch 10 · SZXCHI64005Y · ETA to DALLAS
104 25-050 replacement Infill Pack 1 (Balance IP21 and IP51 )
Cheshire Elementary School · Aluminum panel
PO NA
2 notes
  • task has no Need By date
  • new ETA Apr 21, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-050 - Cheshire Elementary School - Infill Pack 1 - Remake panels
container · 97% · job 25-050 + container SZXCHI64005Y
Apr 28, 2026 → Apr 21, 2026 -7d
TAKA: 2026-04-21 to DALLAS
Not assessed Never Needs review
Batch 11 · SZXCHI64006Y · ETA to DALLAS
121 25-213 MOCK UP
Waxahachie ISD Creek HS Frame & BCCB- Mock Up · MOCKUP
PO NA
2 notes
  • task has no Need By date
  • vessel_loading: implausible year 2030 ('4/25/2030 -')
AIR 25-213 - Waxahachie ISD Creek HS - SAMP (EXPEDITED) - TAKA- PO APPROVAL
fuzzy · 75% · only TAKA task for job 25-213
1 candidate
none → Apr 29, 2026
TAKA: 2026-04-29 to DALLAS
Not assessed Never Needs review
125 25-057 MP1 Remakes
Montage at Midtown · ST01 & ST03 Aluminum frame
PO NA
2 notes
  • task has no Need By date
  • vessel_loading: implausible year 2030 ('4/25/2030 -')
AIR 25-057-10 - Montage at Midtown
fuzzy · 84% · task title has no pack code to confirm MP1
1 candidate
none → Apr 29, 2026
TAKA: 2026-04-29 to DALLAS
Not assessed Never Needs review
126 25-050 - - Infill Pack 1---IP31--1PC
Cheshire Elementary School · Aluminum panel
PO NA
2 notes
  • task has no Need By date
  • vessel_loading: implausible year 2030 ('4/25/2030 -')
AIR 25-050 - Cheshire Elementary School - Infill Pack 1 - Remake panels
fuzzy · 90% · job 25-050 + pack IP1; close runner-up
3 candidates
Apr 28, 2026 → Apr 29, 2026 +1d
TAKA: 2026-04-29 to DALLAS
Not assessed Never Needs review
Batch 13 · SZXCHI65001Y · ETA to DALLAS
152 25-213 - Mock Up (Replaced Alu panel )
Waxahachie ISD Creek HS Frame & BCCB- · Mock Up
PO NA
3 notes
  • dispatch date is unrecognised date format (KE320/02MAY)
  • metal_ready: implausible year 2030 ('4/27/2030 -')
  • container_dispatch: unrecognised date format ('KE320/02MAY')
AIR 25-213 - Waxahachie ISD Creek HS - SAMP (EXPEDITED) - TAKA- PO APPROVAL
fuzzy · 75% · only TAKA task for job 25-213
1 candidate
none → May 04, 2026
TAKA: 2026-05-04 to DALLAS
Not assessed Never Needs review
Batch 22 · SZXCHI65005Y · ETA to DALLAS
190 24-075 - -Cube Picket Mock Up
DFW CTAE AREA C4 EXTERIOR · Cube Picket Mock Up
PO 24-075-019
1 note
  • la_need_by: unrecognised date format ('24-075-019')
AIR 24-075 - DFW CTAE - AREA C4 - EXTERIOR PICKET- IP1 Pending Panel AML -TAKA
fuzzy · 83% · description similarity
3 candidates
Aug 18, 2026 Aug 03, 2026 Sep 10, 2026 → May 22, 2026 -111d
TAKA: 2026-05-22 to DALLAS
On track
83d slack
Never Needs review
Batch 24 · SZXCHI65007Y · ETA to DALLAS
205 24-040 -- 2MP2 insert
Project Meadow - PH2 Aluminum · INSERT
PO 24-040-026
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP2
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → May 28, 2026 -172d
TAKA: 2026-05-28 to DALLAS
On track
171d slack
Never Needs review
Batch 25 · SZXLAX65277X · ETA to LA
209 25-033 - - MP1 (part of materails)
East Montgomery - Glass stair · mirror finish tube
PO NA
1 note
  • new ETA Jun 16, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
fuzzy · 90% · job 25-033 + pack MP1
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Jun 16, 2026 -153d
TAKA: 2026-06-02 to LA
On track
157d slack
Never Needs review
Batch 26 · SZXLAX65356X · ETA to LA
215 25-033 - - MP1 ( 77pcs WP104VC)
East Montgomery - Glass stair · mirror finish tube
PO NA
1 note
  • new ETA Jun 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
fuzzy · 90% · job 25-033 + pack MP1
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Jun 25, 2026 -144d
TAKA: 2026-06-11 to LA
On track
148d slack
Never Needs review
221 25-038 - - MP1
East Dallas Government Center · SOLO POST
PO 25-038-010
OCEAN 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm MP1
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Jun 25, 2026 -144d
TAKA: 2026-06-11 to LA
On track
138d slack
Never Needs review
222 25-115 - - MP1( parts of materails)
Garden City High School · BEACON -FSR POST---PC COLOR
PO 25-115-005
1 note
  • new ETA Jun 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-115 - Garden City - P02 - MP1 Remake -TAKA
fuzzy · 90% · job 25-115 + pack MP1
2 candidates
Nov 13, 2026 Nov 06, 2026 Nov 02, 2026 → Jun 25, 2026 -130d
TAKA: 2026-06-11 to LA
On track
141d slack
Never Needs review
Batch 28 · SZXCHI65008Y · ETA to DALLAS
229 24-040 -2MP2 - 2CN01
Project Meadow · CONNECTOR
PO 24-020-024
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP2
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → May 31, 2026 -169d
TAKA: 2026-05-31 to DALLAS
On track
167d slack
Never Needs review
232 24-201 3MP2 (Except 1pc 24201-3P02R1)
McDaniel - PHASE 3 · CABLE POST
PO 24-021-016
1 note
  • task has no Need By date
AIR 24-201 - McDaniel
fuzzy · 84% · task title has no pack code to confirm 3MP2
1 candidate
none → May 31, 2026
TAKA: 2026-05-31 to DALLAS
Not assessed Never Needs review
Batch 29 · SZXLAX66085X · ETA to LA
236 25-033 - - MP1 ( 3PCS TU38.1x1.8-17)
East Montgomery - Glass stair · mirror finish tube
PO 25-033-006
1 note
  • new ETA Jul 02, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
fuzzy · 90% · job 25-033 + pack MP1
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Jul 02, 2026 -137d
TAKA: 2026-06-18 to LA
On track
141d slack
Never Needs review
237 25-115 - - MP1 (Balance materails)
Garden City High School · BEACON -FSR POST---PC COLOR
PO 25-115-005
1 note
  • new ETA Jul 02, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-115 - Garden City - P02 - MP1 Remake -TAKA
fuzzy · 90% · job 25-115 + pack MP1
2 candidates
Nov 13, 2026 Nov 06, 2026 Nov 02, 2026 → Jul 02, 2026 -123d
TAKA: 2026-06-18 to LA
On track
134d slack
Never Needs review
250 ST26010(P.O.NO:002944)
Offshore Stock Order 2026 · Offshore Stock Order 2026
PO 002944
4 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Jul 02, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
  • order_date: unrecognised date format ('002944')
OCEAN April Offshore Stock Order 2026 - Offshore Stock Order 2026
po · 100% · PO 002944
none → Jul 02, 2026
TAKA: 2026-06-18 to LA
Not assessed Never Needs review
Batch 30 · SZXLAX66099X · ETA to LA
254 25-038 -- GP1
East Dallas Government Center · CERAMIC FRIT GLASS
PO 25-038-009
OCEAN 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm GP1
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Jul 07, 2026 -132d
TAKA: 2026-06-23 to LA
On track
126d slack
Never Needs review
259 TSC-ST26010 PO.No.002944
April Offshore Stock · STOCK ORDER
PO 002944
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Jul 07, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN April Offshore Stock Order 2026 - Offshore Stock Order 2026
po · 100% · PO 002944
none → Jul 07, 2026
TAKA: 2026-06-23 to LA
Not assessed Never Needs review
Batch 31 · SZXCHI66002Y · ETA to DALLAS
261 25-118 - - Mock Up
NWISD · VORTEX POST
PO 25-118-009
AIR 25-118 - NWISD - PICKET MOCK-UP #2 - TAKA
fuzzy · 74% · description similarity; close runner-up
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Jun 11, 2026 -165d
TAKA: 2026-06-11 to DALLAS
On track
157d slack
Never Needs review
264 25-051 - - Mock Up
Ball State Performing Arts Center · MOCK UP --SW7048
PO 25-051-004
1 note
  • new ETA Jun 11, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-051 - Ball State Performing Arts Center - IP1 - TAKA
fuzzy · 94% · description similarity
2 candidates
Nov 02, 2026 Oct 19, 2026 Oct 12, 2026 → Jun 11, 2026 -123d
TAKA: 2026-06-11 to DALLAS
On track
139d slack
Never Needs review
Batch 32 · SZXLAX66099X · ETA to LA
271 25-038 -- GP1 (Except 1pc 25038-G08 )
East Dallas Government Center · CERAMIC FRIT GLASS
PO 25-038-009
OCEAN 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm GP1
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Jul 07, 2026 -132d
TAKA: 2026-06-23 to LA
On track
126d slack
Never Needs review
277 TSC-ST26010 PO.No.002944
April Offshore Stock · STOCK ORDER
PO 002944
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Jul 07, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN April Offshore Stock Order 2026 - Offshore Stock Order 2026
po · 100% · PO 002944
none → Jul 07, 2026
TAKA: 2026-06-23 to LA
Not assessed Never Needs review
Batch 33 · SZXCHI66003Y · ETA to DALLAS
283 24-201 3MP2 (balance 1pc 24201-3P02R1)
McDaniel - PHASE 3 · CABLE POST
PO 24-021-016
1 note
  • task has no Need By date
AIR 24-201 - McDaniel
fuzzy · 84% · task title has no pack code to confirm 3MP2
1 candidate
none → Jun 14, 2026
TAKA: 2026-06-14 to DALLAS
Not assessed Never Needs review
284 24-201 - - 3MP3
McDaniel · BENT TUBE
PO 24-201-017
1 note
  • task has no Need By date
AIR 24-201 - McDaniel
fuzzy · 84% · task title has no pack code to confirm 3MP3
1 candidate
none → Jun 14, 2026
TAKA: 2026-06-14 to DALLAS
Not assessed Never Needs review
285 24-040 - Mock Up
Project Meadow - · MOCK UP--steel PC35
PO 24-040-027
AIR 24-040 - Project Meadow -2MP7 - TAKA
fuzzy · 85% · description similarity; close runner-up
3 candidates
Nov 13, 2026 Nov 10, 2026 Nov 23, 2026 → Jun 14, 2026 -162d
TAKA: 2026-06-14 to DALLAS
On track
146d slack
Never Needs review
Batch 34 · SZXCHI66004Y · ETA to DALLAS
291 25-029 - - Mock Up
Richardson City Hall · SS316 SOLO POST-11pcs
PO 25-029-002
AIR 25-029 - Richardson - MP1 - TAKA
fuzzy · 83% · description similarity; close runner-up
3 candidates
Nov 30, 2026 Nov 09, 2026 Nov 23, 2026 → Jun 25, 2026 -151d
TAKA: 2026-06-25 to DALLAS
On track
152d slack
Never Needs review
292 26-046 Mock Up
Cobb Galleria · With Dark Granite for the 43"h mockup and Pure clear anodized for the 14" h version
PO 26-046-002
AIR 26-046 Cobb Galleria - IP1 - TAKA
fuzzy · 87% · description similarity; close runner-up
2 candidates
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Jun 25, 2026 -125d
TAKA: 2026-06-25 to DALLAS
On track
106d slack
Never Needs review
293 25-203 - - TAKA
J Marshall HS - COLOR SAMPLE · COLOR Sample -SW6070
PO 25-203-001
1 note
  • new ETA Jun 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-203 - J Marshall HS - MP1 - TAKA
fuzzy · 87% · only TAKA task for job 25-203
1 candidate
Nov 11, 2026 Oct 20, 2026 Nov 04, 2026 → Jun 25, 2026 -132d
TAKA: 2026-06-25 to DALLAS
On track
133d slack
Never Needs review
Batch 35 · SZXLAX66302X · ETA to LA
312 TSC-ST26010 PO.No.002944
April Offshore Stock · STOCK ORDER
PO 002944
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Jul 14, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN April Offshore Stock Order 2026 - Offshore Stock Order 2026
po · 100% · PO 002944
none → Jul 14, 2026
TAKA: 2026-06-30 to LA
Not assessed Never Needs review
Batch 36 · SZXLAX66386X · ETA to LA
318 25-038 -- GP1 (balance 1pc )
East Dallas Government Center · CERAMIC FRIT GLASS
PO 25-038-009
OCEAN 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm GP1
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Jul 21, 2026 -118d
TAKA: 2026-07-07 to LA
On track
112d slack
Never Needs review
Batch 37 · SZXLAX67036X · ETA to LA
330 24-040 - - 2MP3
Project Meadow - PH2 Aluminum · Aluminum post--PC40
PO NA
OCEAN 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP3
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Aug 07, 2026 -101d
TAKA: 2026-07-24 to LA
On track
105d slack
Never Needs review
334 TSC-ST26010 PO.No.002944
April Offshore Stock · STOCK ORDER
PO 002944
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Aug 07, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN April Offshore Stock Order 2026 - Offshore Stock Order 2026
po · 100% · PO 002944
none → Aug 07, 2026
TAKA: 2026-07-24 to LA
Not assessed Never Needs review
Batch 39 · SZXCHI67001Y · ETA to DALLAS
346 26-086 -Mock Up
TCAT Memphis - FOLD - Mock Up · mock up--MC75
PO 26-086-001
1 note
  • new ETA Jul 05, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-086 - TCAT Memphis - MP1 -TAKA
fuzzy · 86% · only TAKA task for job 26-086
1 candidate
Sep 25, 2026 Sep 18, 2026 Sep 14, 2026 → Jul 05, 2026 -71d
TAKA: 2026-07-05 to DALLAS
On track
79d slack
Never Needs review
347 25-049 - - Mock Up
Redding Rancheria - STRUC · mock up--MC73
PO 25-049-002
1 note
  • new ETA Jul 05, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-049 - Redding Rancheria - IP1 - TAKA
fuzzy · 90% · description similarity
3 candidates
Dec 18, 2026 Dec 04, 2026 Dec 22, 2026 → Jul 05, 2026 -170d
TAKA: 2026-07-05 to DALLAS
On track
163d slack
Never Needs review
Batch 40 · SZXCHI67002Y · ETA to DALLAS
357 25-041 GP1 Remake
Jackson Walker · GLASS
PO 25-041-027
1 note
  • new ETA Jul 06, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
po · 100% · PO 25-041-027
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Jul 06, 2026 -94d
TAKA: 2026-07-06 to DALLAS
At risk: Need By
-17d slack
Never Needs review
366 26-028 -Beacon Mesh Mock Up
Sapulpa High School · Beacon Mesh Mock Up
PO 26-028-001
AIR 26-028 - Sapulpa High School - GP1 - TAKA
fuzzy · 90% · description similarity; close runner-up
3 candidates
Nov 06, 2026 Oct 30, 2026 Nov 23, 2026 → Jul 06, 2026 -140d
TAKA: 2026-07-06 to DALLAS
On track
118d slack
Never Needs review
Batch 41 · SZXCHI67003Y · ETA to DALLAS
371 TSC-ST26029 (only sent aluminum 1/8" mill finish firsstly )
Panelscape sample · Panelscape sample
PO VS2026-025
3 notes
  • dispatch date is unrecognised date format (07JUL / flight no.JL88)
  • new ETA Jul 10, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
  • container_dispatch: unrecognised date format ('07JUL / flight no.JL88')
AIR Panelscape samples 2"x2"
po · 100% · PO VS2026-025
Jul 13, 2026 → Jul 10, 2026 -3d
TAKA: 2026-07-10 to DALLAS
Not assessed Never Needs review
372 25-050 - Infill Pack 1 Remakes
Cheshire Elementary School · ALU PNAEL -3 color
PO 25-050-010
2 notes
  • dispatch date is unrecognised date format (07JUL / flight no.JL88)
  • container_dispatch: unrecognised date format ('07JUL / flight no.JL88')
AIR 25-050 - Cheshire Elementary School - Infill Pack 1 - Remake panels
fuzzy · 90% · job 25-050 + pack IP1; close runner-up
3 candidates
Apr 28, 2026 → Jul 10, 2026 +73d
TAKA: 2026-07-10 to DALLAS
Not assessed Never Needs review
375 24-020 Brackets
LHHS#2 · Brackets
PO 24-020-054
2 notes
  • dispatch date is unrecognised date format (07JUL / flight no.JL88)
  • container_dispatch: unrecognised date format ('07JUL / flight no.JL88')
AIR 24-020 - LHHS#2 - 3IP3 -TAKA
fuzzy · 71% · description similarity; close runner-up
2 candidates
Dec 17, 2026 Dec 10, 2026 Dec 04, 2026 → Jul 10, 2026 -147d
TAKA: 2026-07-10 to DALLAS
Not assessed Never Needs review
376 26-028 Beacon Glass Mock Up
Sapulpa High School · Beacon Glass Mock Up
PO 26-028-002
2 notes
  • dispatch date is unrecognised date format (07JUL / flight no.JL88)
  • container_dispatch: unrecognised date format ('07JUL / flight no.JL88')
AIR 26-028 - Sapulpa High School - GP1 - TAKA
fuzzy · 90% · description similarity; close runner-up
3 candidates
Nov 06, 2026 Oct 30, 2026 Nov 23, 2026 → Jul 10, 2026 -136d
TAKA: 2026-07-10 to DALLAS
Not assessed Never Needs review
Batch 42 · SZXCHI67004Y · ETA to DALLAS
385 26-062 - - Mock Up
TAMU COD - Gaston Entry · MOCK UP
PO 26-062-001
AIR 26-062 - TAMU COD- MP2- TAKA
fuzzy · 80% · only TAKA task for job 26-062
1 candidate
Oct 21, 2026 Oct 07, 2026 Oct 22, 2026 → Jul 13, 2026 -101d
TAKA: 2026-07-13 to DALLAS
On track
94d slack
Never Needs review
Batch 46 · SZXLAX67350X · ETA to LA
418 25-029 MP1
Richardson City Hall · FSR POST
PO 25-029-003
1 note
  • new ETA Aug 20, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-029 - Richardson - MP1 - TAKA
fuzzy · 100% · job 25-029 + pack MP1
3 candidates
Nov 30, 2026 Nov 09, 2026 Nov 23, 2026 → Aug 20, 2026 -95d
TAKA: 2026-08-06 to LA
On track
102d slack
Never Needs review
Batch 47 · SZXLAX68039X · ETA to LA
433 24-075 -- MP5
DFW CTAE · PNAEL FRAME PLATE
PO 24-075-023
1 note
  • new ETA Aug 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 24-075 - DFW CTAE - AREA C4 - EXTERIOR PICKET- IP1 Pending Panel AML -TAKA
po · 100% · PO 24-075-023
Aug 18, 2026 Aug 03, 2026 Sep 10, 2026 → Aug 28, 2026 -13d
TAKA: 2026-08-14 to LA
At risk: LA + Need By
-10d slack
Never Needs review
Batch 49 · SZXCHI67008Y · ETA to DALLAS
443 25-076 - - IP4
Norton ES · Aluminum frame panel
PO NA
1 note
  • task has no Need By date
AIR 25-076 - Norton ES - IP4 Remake - TAKA- PO APPROVAL
fuzzy · 90% · job 25-076 + pack IP4; close runner-up
2 candidates
Oct 20, 2026 none → Jul 29, 2026
TAKA: 2026-07-29 to DALLAS
Not assessed Never Needs review
445 24-040 - 2MP4 ( sent 2CN12 fristly)
Project Meadow - Ph2 level 8 · FITTINGS
PO 24-040-029
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP4
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Jul 29, 2026 -110d
TAKA: 2026-07-29 to DALLAS
On track
108d slack
Never Needs review
Batch 50 · SZXCHI68001Y · ETA to DALLAS
450 24-040 - 2MP4 ( balance 2CN13)
Project Meadow - Ph2 level 8 · FITTINGS
PO 24-040-029
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP4
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Aug 04, 2026 -104d
TAKA: 2026-08-04 to DALLAS
On track
102d slack
Never Needs review
451 24-040 - - 2IP2
Project Meadow - Ph2 level 8 · ALU PICKET PANEL
PO 24-040-030
AIR 24-040 - Project Meadow - 2IP02 - TAKA
fuzzy · 90% · job 24-040 + pack 2IP2; close runner-up
3 candidates
Nov 20, 2026 Nov 13, 2026 none → Aug 04, 2026
TAKA: 2026-08-04 to DALLAS
On track
102d slack
Never Needs review
454 26-065 MOCKUP
VUMC Link - BEACON CABLE-NET - Mock Up · BEACON CABLE-NET - Mock Up
PO 26-065-001
2 notes
  • task has no Need By date
  • new ETA Aug 04, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-065 - VUMC Link - BEACON CABLE-NET - Mock Up - TAKA- PO APPROVAL
po · 100% · PO 26-065-001
Aug 21, 2026 none → Aug 04, 2026
TAKA: 2026-08-04 to DALLAS
Not assessed Never Needs review
457 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Aug 04, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Aug 04, 2026 -65d
TAKA: 2026-08-04 to DALLAS
At risk: Need By
-47d slack
Never Needs review
460 TSC-ST26029 (20pcs 14GA ZINC RICH primer)
Panelscape sample · Panelscape sample
PO VS2026-025
2 notes
  • task has no Need By date
  • new ETA Aug 04, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR Panelscape samples 2"x2"
po · 100% · PO VS2026-025
Jul 13, 2026 → Aug 04, 2026 +22d
TAKA: 2026-08-04 to DALLAS
Not assessed Never Needs review
461 26-028 MOCK UP ( clamp FOR 21.52mm glass )
Sapulpa High School · Beacon Glass Mock Up
PO 26-028-002
AIR 26-028 - Sapulpa High School - GP1 - TAKA
fuzzy · 90% · description similarity; close runner-up
3 candidates
Nov 06, 2026 Oct 30, 2026 Nov 23, 2026 → Aug 04, 2026 -111d
TAKA: 2026-08-04 to DALLAS
On track
88d slack
Never Needs review
Batch 51 · SZXLAX68130X · ETA to LA
463 24-075 - IP1
DFW CTAE - AREA C4 - EXTERIOR PICKET- · SS316 PANEL FRAME
PO 24-075-022
1 note
  • task has no Need By date
OCEAN 24-075 - DFW CTAE - AREA C4 (BRIDGES) - IP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 24-075 + pack IP1; close runner-up
3 candidates
Sep 10, 2026 none → Sep 03, 2026
TAKA: 2026-08-20 to LA
On track Never Needs review
Batch 53 · DHL 7057327642 · ETA to DALLAS
479 25-142 MP1 GAEP121U
QTS DFW2 DC3 · GAEP121U
PO NA
2 notes
  • task has no Need By date
  • new ETA Aug 14, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-142 - QTS DFW2 DC3 - MP1 - TAKA
fuzzy · 100% · job 25-142 + pack MP1
1 candidate
Aug 12, 2026 Aug 21, 2026 → Aug 14, 2026 -7d
TAKA: 2026-08-14 to DALLAS
Not assessed Never Needs review
480 25-192 Anti Reflective Glass
WSVN 7 · GLASS SAMPLE
PO NA
AIR 25-192 - WSVN 7 - MP1 - TAKA
fuzzy · 75% · description similarity
3 candidates
Oct 06, 2026 Sep 22, 2026 Oct 01, 2026 → Aug 14, 2026 -48d
TAKA: 2026-08-14 to DALLAS
On track
50d slack
Never Needs review
481 color sample for 24-075 IP1
DFW CTAE AREA C4 · color sample
PO NA
1 note
  • task has no Need By date
AIR 24-075 - DFW CTAE - AREA C4 (BRIDGES) - IP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 24-075 + pack IP1; close runner-up
3 candidates
Sep 10, 2026 none → Aug 14, 2026
TAKA: 2026-08-14 to DALLAS
Not assessed Never Needs review
Batch 54 · SZXLAX68319X · ETA to LA
483 TSC-ST26023 SAMPLE STOCK (part of materails)
SAMPLE STOCK · SAMPLE STOCK
PO VS2026-026
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Sep 16, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN SAMPLE STOCK - TAKA
po · 100% · PO VS2026-026
Sep 24, 2026 → Sep 16, 2026 -8d
TAKA: 2026-09-02 to LA
Not assessed Never Needs review
Batch 58 · SZXLAX69067X · ETA to LA
521 24-075 - IP1
DFW CTAE AREA C4 · 12mm LASER CUT PANEL - PP11--color as sample
PO 24-075-027
2 notes
  • task has no Need By date
  • new ETA Oct 01, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 24-075 - DFW CTAE - AREA C4 (BRIDGES) - IP1 - TAKA- PO APPROVAL
po · 100% · PO 24-075-027
Sep 10, 2026 none → Oct 01, 2026
TAKA: 2026-09-17 to LA
At risk: LA Never Needs review
527 TSC-ST26023 SAMPLE STOCK (Balance Materails)
SAMPLE STOCK · SAMPLE STOCK
PO VS2026-026
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Oct 01, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN SAMPLE STOCK - TAKA
po · 100% · PO VS2026-026
Sep 24, 2026 → Oct 01, 2026 +7d
TAKA: 2026-09-17 to LA
Not assessed Never Needs review
529 24-040 -MP1 (Ship fittings firstly)
Project Meadow - PH4 Penthouse · ALU PANEL---PC40
PO 24-040-032
OCEAN 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm MP1
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Oct 01, 2026 -46d
TAKA: 2026-09-17 to LA
On track
50d slack
Never Needs review
Batch 59 · SZXCHI69002Y · ETA to DALLAS
531 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Sep 10, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Sep 10, 2026 -28d
TAKA: 2026-09-10 to DALLAS
At risk: Need By
-84d slack
Never Needs review
532 24-040 MP5
Project Meadow · SS316 CLADDING
PO 24-040-036
1 note
  • task has no Need By date
AIR 24-040 - Project Meadow - MP5 Cladding - TAKA- PO APPROVAL
fuzzy · 90% · job 24-040 + pack MP5; close runner-up
3 candidates
Sep 04, 2026 none → Sep 10, 2026
TAKA: 2026-09-10 to DALLAS
Not assessed Never Needs review
537 26-086 - - MP1
TCAT Memphis · FOLD POST-SS316/304
PO 26-086-003
1 note
  • new ETA Sep 10, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-086 - TCAT Memphis - MP1 -TAKA
fuzzy · 100% · job 26-086 + pack MP1
1 candidate
Sep 25, 2026 Sep 18, 2026 Sep 14, 2026 → Sep 10, 2026 -4d
TAKA: 2026-09-10 to DALLAS
On track
9d slack
Never Needs review
538 24-040 2MP5 (Ship 24040-2CN01 and 24040-2SL firstly)
Project Meadow - PH2 Level 10 · ALU POST
PO 24-040-034
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP5
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Sep 10, 2026 -67d
TAKA: 2026-09-10 to DALLAS
On track
65d slack
Never Needs review
Batch 60 · SZXLAX69152X · ETA to LA
541 24-040 -MP1
Project Meadow - PH4 Penthouse · ALU PANEL---PC40
PO 24-040-032
OCEAN 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm MP1
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Oct 08, 2026 -39d
TAKA: 2026-09-24 to LA
On track
43d slack
Never Needs review
543 26-061 Metal Pack 1
Warriors FH · VORTEX POST
PO 26-061-002
OCEAN No task
PO 26-061-002 is on 2 tasks
2 candidates
none → Oct 08, 2026
TAKA: 2026-09-24 to LA
Not assessed Never Needs review
544 25-125 -- GP1 (except 2pc 25125-G29-V1 & 1pc 25125-G11-V1)
CACC Aviation Hangar · GLASS
PO 25-125-005
1 note
  • new ETA Oct 08, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-125 - CACC Aviation Hangar - GP1 -TAKA
po · 100% · PO 25-125-005
Oct 06, 2026 Sep 22, 2026 Oct 22, 2026 → Oct 08, 2026 -14d
TAKA: 2026-09-24 to LA
At risk: LA + Need By
-2d slack
Never Needs review
547 TSC-ST26023 SAMPLE STOCK (Balance 1pc PG-11)
SAMPLE STOCK · SAMPLE STOCK
PO VS2026-026
3 notes
  • task has no LA Need By date
  • task has no Need By date
  • new ETA Oct 08, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN SAMPLE STOCK - TAKA
po · 100% · PO VS2026-026
Sep 24, 2026 → Oct 08, 2026 +14d
TAKA: 2026-09-24 to LA
Not assessed Never Needs review
Batch 62 · SZXCHI69003Y · ETA to DALLAS
556 25-038 - GP1 REMAKE
East Dallas Government Center · GLASS
PO 25-038-011
AIR 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm GP1
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Sep 20, 2026 -57d
TAKA: 2026-09-20 to DALLAS
On track
45d slack
Never Needs review
558 24-040 - - 2IP3
Project Meadow - PH2 Level 10 · ALU PICKET PANEL 48.3
PO 24-040-035
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2IP3
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Sep 20, 2026 -57d
TAKA: 2026-09-20 to DALLAS
On track
55d slack
Never Needs review
559 24-040 2MP5
Project Meadow - PH2 Level 10 · ALU POST
PO 24-040-034
AIR 24-040 - Project Meadow - 2P02 - TAKA
fuzzy · 84% · task title has no pack code to confirm 2MP5
3 candidates
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Sep 20, 2026 -57d
TAKA: 2026-09-20 to DALLAS
On track
55d slack
Never Needs review
565 25-149 MP1
New Albany · ALU FRAME POST---PC41
PO 25-149-001
2 notes
  • task has no Need By date
  • new ETA Sep 20, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-149 - New Albany - MP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 25-149 + pack MP1
1 candidate
none → Sep 20, 2026
TAKA: 2026-09-20 to DALLAS
Not assessed Never Needs review
568 TSC-ST26036
SAMPLE STOCK ORDER #2 - 082126 TAKA · ALU PANEL---20pcs each by air
PO VS2026-034
2 notes
  • task has no Need By date
  • new ETA Sep 20, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR SAMPLE STOCK ORDER #2 - TAKA
po · 100% · PO VS2026-034
Oct 28, 2026 → Sep 20, 2026 -38d
TAKA: 2026-09-20 to DALLAS
Not assessed Never Needs review
Batch 63 · SZXLAX69368X · ETA to LA
572 24-212 1MP1 (except TU38.1X1.8--104EA)
CISD - Crowley High School - Texas - Phase 2, Arena B&C · CIRCA -FSR POST
PO 24-212-014
OCEAN No task
PO 24-212-014 is on 2 tasks
2 candidates
none → Oct 22, 2026
TAKA: 2026-10-08 to LA
Not assessed Never Needs review
575 25-155 MP1 (excpet WP100DC-90EA)
Del Norte · BLADE POST
PO 25-155-003
1 note
  • new ETA Oct 22, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-155 - Del Norte - MP1 -TAKA
po · 100% · PO 25-155-003
Nov 02, 2026 Oct 19, 2026 Oct 28, 2026 → Oct 22, 2026 -6d
TAKA: 2026-10-08 to LA
On track
11d slack
Never Needs review
577 26-061 -- MP1 ADDITION
Warriors FH · BEACON POST
PO 26-061-002
OCEAN No task
PO 26-061-002 is on 2 tasks
2 candidates
none → Oct 22, 2026
TAKA: 2026-10-08 to LA
Not assessed Never Needs review
Batch 64 · SZXLAX69483X · ETA to LA
582 25-096 3GP1 (balance parts)
Cicero North HS Pool · 21.52pvb glass
PO 25-096-002
1 note
  • new ETA Oct 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-096 - Cicero North HS Pool - 3GP1 - TAKA
fuzzy · 100% · job 25-096 + pack 3GP1
2 candidates
Oct 22, 2026 Oct 08, 2026 Oct 22, 2026 → Oct 28, 2026 +6d
TAKA: 2026-10-14 to LA
At risk: LA + Need By
-6d slack
Never Needs review
584 24-212 1MP1 (Balance TU38.1X1.8--104EA)
CISD - Crowley High School - Texas - Phase 2, Arena B&C · CIRCA -FSR POST
PO 24-212-014
OCEAN No task
PO 24-212-014 is on 2 tasks
2 candidates
none → Oct 28, 2026
TAKA: 2026-10-14 to LA
Not assessed Never Needs review
591 25-145- MP1
Kingsport Library · FLAT BAR POST
PO 26-155-003
1 note
  • new ETA Oct 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-145 Kingsport Library - MP1 - TAKA
container · 97% · job 25-145 + container SZXLAX69483X
Oct 30, 2026 Oct 16, 2026 none → Oct 28, 2026
TAKA: 2026-10-14 to LA
On track
2d slack
Never Needs review
592 25-203 - - MP1 (Except PB105FL)
J Marshall HS · FOLD POST
PO NA
1 note
  • new ETA Oct 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-203 - J Marshall HS - MP1 - TAKA
container · 97% · job 25-203 + container SZXLAX69483X
Nov 11, 2026 Oct 20, 2026 Nov 04, 2026 → Oct 28, 2026 -7d
TAKA: 2026-10-14 to LA
On track
14d slack
Never Needs review
Batch 66 · SZXCHI69005Y · ETA to DALLAS
601 25-051 - - MP1
Ball State Performing Arts Center- EXPEDITED (POST) · STRUC POST
PO 25-051-006
2 notes
  • task has no Need By date
  • new ETA Sep 29, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-051 - Ball State Performing Arts Center- EXPEDITED (POST)- MP1 - TAKA- PO APPROVAL
po · 100% · PO 25-051-006
Sep 29, 2026 none → Sep 29, 2026
TAKA: 2026-09-29 to DALLAS
Not assessed Never Needs review
602 TSC-ST26032 Color Chip Samples ( Ship parts firstly )
Color Chip Samples · Color Chip Samples
PO VS2026-031
2 notes
  • task has no Need By date
  • new ETA Sep 29, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR Taka Order - Color Chip Samples - 8-10-2026
po · 100% · PO VS2026-031
Oct 28, 2026 → Sep 29, 2026 -29d
TAKA: 2026-09-29 to DALLAS
Not assessed Never Needs review
Batch 67 · SZXLAX6A088X · ETA to LA
607 25-155 - IP1
Del Norte - · PERFORATED PANEL
PO 25-155-002
OCEAN No task
PO 25-155-002 is on 2 tasks
2 candidates
none → Nov 04, 2026
TAKA: 2026-10-21 to LA
Not assessed Never Needs review
Batch 68 · flight booked SZXCHI6A001Y · ETA to DALLAS
618 25-213 sample
Waxahachie ISD Creek HS · SS PANEL SAMPLE
PO 25-213-003
2 notes
  • task has no Need By date
  • new ETA Oct 05, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-213 - Waxahachie ISD Creek HS - SAMP (EXPEDITED) - TAKA- PO APPROVAL
po · 100% · PO 25-213-003
none → Oct 05, 2026
TAKA: 2026-10-05 to DALLAS
Not assessed Never Needs review
Batch 69 · DHL 11 2151 9350 · ETA to DALLAS
622 26-061 MP1
Warrior MP1 · BP150BC-V2
PO 26-061-003
2 notes
  • dispatch date is will_be_informed (will be informed)
  • new ETA Oct 05, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-061 - Warriors FH - MP1 - BP150BC-V2 - TAKA
po · 100% · PO 26-061-003
Oct 02, 2026 Oct 02, 2026 Oct 06, 2026 → Oct 05, 2026 -1d
TAKA: 2026-10-05 to DALLAS
Not assessed Never Needs review
Batch 70 · SZXCHI6A002Y · ETA to DALLAS
627 25-051 - - IP1
Ball State Performing Arts Center · 10MM Aluminum panel--SW7048
PO 25-051-005
1 note
  • new ETA Oct 09, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-051 - Ball State Performing Arts Center - IP1 - TAKA
po · 100% · PO 25-051-005
Nov 02, 2026 Oct 19, 2026 Oct 12, 2026 → Oct 09, 2026 -3d
TAKA: 2026-10-09 to DALLAS
On track
23d slack
Never Needs review
Batch 71 · SZXLAX6A132X · ETA to LA
636 26-081 - - IP1
Stanford CHS · PERFORATED PANEL
PO 26-081-001
OCEAN No task
PO 26-081-001 is on 2 tasks
2 candidates
none → Nov 10, 2026
TAKA: 2026-10-27 to LA
Not assessed Never Needs review
Batch 72 · SZXCHI6A003Y · ETA to DALLAS
643 26-127 Mock Up
Gainesville PD · Mock Up ---RAL5022
PO 26-127-001
1 note
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-127 - Gainesville PD - Mock Up - TAKA
po · 100% · PO 26-127-001
Oct 08, 2026 Sep 30, 2026 Oct 22, 2026 → Oct 15, 2026 -7d
TAKA: 2026-10-15 to DALLAS
At risk: Need By
-13d slack
Never Needs review
645 25-041- GP1
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 90% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Oct 15, 2026 +7d
TAKA: 2026-10-15 to DALLAS
At risk: Need By
-119d slack
Never Needs review
646 25-038 -GP2
East Dallas · GLASS
PO 25-038-012
AIR 25-038 - East Dallas - G08 - TAKA
fuzzy · 84% · task title has no pack code to confirm GP2
2 candidates
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Oct 15, 2026 -32d
TAKA: 2026-10-15 to DALLAS
On track
20d slack
Never Needs review
648 26-076 - - Mock Up
Prairie SS Center - Blade SM · Blade WM- Mock Up
PO 26-076-002
2 notes
  • task has no Need By date
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-076 - Prairie SS Center - Blade WM- Mock Up - TAKA- PO APPROVAL
po · 100% · PO 26-076-002
Oct 16, 2026 none → Oct 15, 2026
TAKA: 2026-10-15 to DALLAS
Not assessed Never Needs review
649 26-076 -- Mock Up (except glass)
Prairie SS Center - Blade GLASS · Blade Glass - Mock Up
PO 26-076-001
1 note
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-076 - Prairie SS Center - Blade Glass - Mock Up - TAKA
po · 100% · PO 26-076-001
Oct 23, 2026 Oct 16, 2026 Oct 22, 2026 → Oct 15, 2026 -7d
TAKA: 2026-10-15 to DALLAS
On track
2d slack
Never Needs review
Batch 73 · SZXLAX6A235X · ETA to LA
654 25-206 2IP1
Newman Smith HS - Stair 4 · wire mesh panel
PO 25-206-004
OCEAN No task
PO 25-206-004 is on 2 tasks
2 candidates
none → Nov 21, 2026
TAKA: 2026-11-07 to LA
Not assessed Never Needs review
656 26-088 AML (Sent 3" SQ.TUBE firstly)
Eastern Hills · FITTINGS
PO 26-088-004
1 note
  • 2 lines would set this task's ETA: row 656 (2026-11-21), row 752 (2026-12-10). Keep one, discard the rest.
OCEAN 26-088 - Eastern Hills - AML - TAKA
po · 100% · PO 26-088-004
Nov 20, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
At risk: LA + Need By
-1d slack
Never Needs review
Batch 74 · flight booked · ETA to DALLAS
663 26-076 -- Mock Up (only glass)
Prairie SS Center - Blade GLASS · Blade Glass - Mock Up
PO 26-076-001
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-076 - Prairie SS Center - Blade Glass - Mock Up - TAKA
po · 100% · PO 26-076-001
Oct 23, 2026 Oct 16, 2026 Oct 22, 2026 → Oct 25, 2026 +3d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-8d slack
Never Needs review
664 25-118 - SAMPLE (except 1pc)
NWISD · GLASS SAMPLE
PO 25-118-011
2 notes
  • task has no Need By date
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-118 - NWISD - SAMP - TAKA
po · 100% · PO 25-118-011
Oct 09, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
Not assessed Never Needs review
666 26-089 - - SW7066
SUNY Morrisville · SW7066 color sample
PO 26-089-001
AIR 26-089 - SUNY Morrisville - IP1 - TAKA
fuzzy · 89% · description similarity; close runner-up
3 candidates
Dec 01, 2026 Nov 17, 2026 Dec 03, 2026 → Oct 25, 2026 -39d
TAKA: 2026-10-25 to DALLAS
On track
31d slack
Never Needs review
667 26-102 -- Mock Up
Natatorium NR Dining · SHOE MOCK UP
PO 26-102-004
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-102 - Natatorium NR Dining - Mock Up - SHOE - TAKA
po · 100% · PO 26-102-004
Oct 23, 2026 Oct 16, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-8d slack
Never Needs review
668 26-102 -- Mock Up
Natatorium NR Dining · CIRCA MOCK UP
PO 26-102-003
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-102 - Natatorium NR Dining - Mock Up - CIRCA GLASS - TAKA
po · 100% · PO 26-102-003
Nov 02, 2026 Oct 19, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
On track
2d slack
Never Needs review
669 26-058 - Mock Up
UAH - · beacon mock up
PO 26-058-001
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-058 - UAH - Mock Up - TAKA
po · 100% · PO 26-058-001
Oct 30, 2026 Oct 23, 2026 Nov 09, 2026 → Oct 25, 2026 -15d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-1d slack
Never Needs review
670 24-200 - - 2MP3
North Carolina Education Campus · CONNECTOR
PO 24-200-019
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 24-200 - North Carolina Education Campus - 2MP3 - TAKA
po · 100% · PO 24-200-019
Oct 30, 2026 Oct 23, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-1d slack
Never Needs review
672 26-122 - - MP1
Zipline Tenant Improvement · STRUC POST --PC30
PO 26-122-002
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-122 - Zipline Tenant Improvement - MP1 - TAKA
po · 100% · PO 26-122-002
Nov 06, 2026 Oct 30, 2026 Nov 09, 2026 → Oct 25, 2026 -15d
TAKA: 2026-10-25 to DALLAS
On track
6d slack
Never Needs review
673 26-118 MOCK UP
LeTU CPUC · Wind wall - Mock Up
PO 26-118-001
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-118 - LeTU CPUC - Wind wall - Mock Up - TAKA
po · 100% · PO 26-118-001
Nov 06, 2026 Oct 30, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
On track
6d slack
Never Needs review
674 25-115 - - MP1 Remake
Garden City - P02 · P02 POST--PC36
PO 25-115-007
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-115 - Garden City - P02 - MP1 Remake -TAKA
po · 100% · PO 25-115-007
Nov 13, 2026 Nov 06, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
On track
13d slack
Never Needs review
Batch 75 · no shipment # · ETA to DALLAS
676 25-075 - - IP2 remakes
UM Gem Factory · Cablenet PANEL
PO 25-075-007
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-075 - UM Gem Factory - IP2 remakes - TAKA
po · 100% · PO 25-075-007
Oct 23, 2026 Oct 16, 2026 Nov 02, 2026 → Oct 30, 2026 -3d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-10d slack
Never Needs review
677 26-079 MOCK UP
Old Mill · BLADE WM15
PO 26-079-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-079 - Old Mill - Mock Up - Blade WM - TAKA
po · 100% · PO 26-079-001
Oct 30, 2026 Oct 23, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-3d slack
Never Needs review
678 26-209 - MOCK-UP and color sample
JH Carter -Benjamin Moore 2062-10 SAMP · 8mm x 50mm flat bar mock up
PO 26-209-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-209 - JH Carter -Benjamin Moore 2062-10 SAMP - TAKA
po · 100% · PO 26-209-001
Oct 20, 2026 Oct 13, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-13d slack
Never Needs review
679 25-130 - - Mock Up
Warren School · STRUC MOCK UP-MC71
PO 25-130-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-130 - Warren School - Mock Up - TAKA
po · 100% · PO 25-130-001
Nov 06, 2026 Oct 30, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
On track
4d slack
Never Needs review
680 26-190 MOCK UP
Interstate Sioux Falls · CIRCA CABLE MOCK UP
PO 26-190-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-190 - Interstate Sioux Falls - Mock Up - TAKA
po · 100% · PO 26-190-001
Nov 13, 2026 Nov 06, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
On track
11d slack
Never Needs review
681 25-033 - - MP4
East Montgomery - Stair 06 Handrails · bending tube
PO 25-033-023
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-033 - East Montgomery - Stair 06 Handrails - MP4- TAKA
po · 100% · PO 25-033-023
Nov 06, 2026 Oct 30, 2026 Nov 16, 2026 → Oct 30, 2026 -17d
TAKA: 2026-10-30 to DALLAS
On track
4d slack
Never Needs review
682 25-062 - - IP3
RDNI · PICKET PANEL
PO 25-062-009
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-062 - RDNI - IP3- TAKA
po · 100% · PO 25-062-009
Nov 06, 2026 Oct 30, 2026 Nov 16, 2026 → Oct 30, 2026 -17d
TAKA: 2026-10-30 to DALLAS
On track
4d slack
Never Needs review
684 25-050 - - IP1 & IP2 Remakes
Cheshire Elementary School · IP2 Remakes
PO TAKA COST
4 notes
  • task has no Need By date
  • PO number not recognised: 'TAKA COST'
  • container_dispatch 2026-10-31 differs from batch majority 2026-10-26
  • eta 2026-11-03 differs from batch majority 2026-10-30
AIR 25-050 - Cheshire Elementary School - IP1 & IP2 Remakes - TAKA- PO APPROVAL
fuzzy · 100% · job 25-050 + pack IP1; close runner-up
3 candidates
Oct 30, 2026 none → Nov 03, 2026
TAKA: 2026-11-03 to DALLAS
Not assessed Never Needs review
687 24-040 -- 1MP6
Project Meadow - Additional Glass Scope L10 · U CAP CONNECTOR
PO 24-040-047
3 notes
  • would move the ETA 20 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
  • container_dispatch 2026-10-31 differs from batch majority 2026-10-26
  • eta 2026-11-03 differs from batch majority 2026-10-30
AIR 24-040 - Project Meadow - Additional Glass Scope L10- 1MP6 - TAKA
po · 100% · PO 24-040-047
Nov 13, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 03, 2026 -20d
TAKA: 2026-11-03 to DALLAS
On track
6d slack
Never Needs review
Batch 76 · TAKA COST · ETA to DALLAS
691 24-040 -- 2IP4
Project Meadow - Level 8 Picket · ALU PICKET PANEL
PO 24-040-046
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow - Level 8 Picket- 2IP4 - TAKA
po · 100% · PO 24-040-046
Nov 13, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
692 24-040 -- - 2MP6
Project Meadow - Level 8 Picket · FITTINGS
PO 24-040-045
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow - Level 8 Picket- 2MP6 - TAKA
po · 100% · PO 24-040-045
Nov 13, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
693 24-040 - -2MP7
Project Meadow · FITTINGS
PO 24-040-052
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow -2MP7 - TAKA
po · 100% · PO 24-040-052
Nov 13, 2026 Nov 10, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
Batch 77 · no shipment # · ETA to DALLAS
699 25-118 --1MP2 (air parts )
NWISD - PHASE 1 METAL · POST
PO 25-118-013
1 note
  • 2 lines would set this task's ETA: row 699 (2026-11-15), row 754 (2026-12-10). Keep one, discard the rest.
AIR 25-118 - NWISD - PHASE 1 - METAL 1MP2 - TAKA
po · 100% · PO 25-118-013
Dec 04, 2026 Nov 20, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
13d slack
Never Needs review
701 25-206 - - 1MP3
Newman Smith HS Renovation - Stair 14 · CONNECTOR
PO 25-206-005
1 note
  • 2 lines would set this task's ETA: row 701 (2026-11-15), row 719 (2026-11-22). Keep one, discard the rest.
AIR 25-206 - Newman Smith HS Renovation - Stair 14 - 1MP3 - TAKA
po · 100% · PO 25-206-005
Nov 27, 2026 Nov 20, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
6d slack
Never Needs review
702 25-206 - -1IP2
Newman Smith HS Renovation - Stair 14 · wire mesh panel
PO 25-206-006
1 note
  • 2 lines would set this task's ETA: row 702 (2026-11-15), row 720 (2026-11-22). Keep one, discard the rest.
AIR 25-206 - Newman Smith HS Renovation - Stair 14 -1IP2 - TAKA
po · 100% · PO 25-206-006
Nov 27, 2026 Nov 20, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
6d slack
Never Needs review
707 25-120 - - 1IP2
Clemson Veterinary(HUB BUILDING) · WM PANEL--pc35
PO 25-120-009
1 note
  • 2 lines would set this task's ETA: row 707 (2026-11-15), row 725 (2026-11-27). Keep one, discard the rest.
AIR 25-120 - Clemson Veterinary - PHASE 2 - 2IP2 - TAKA
po · 100% · PO 25-120-009
Dec 04, 2026 Nov 27, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
13d slack
Never Needs review
718 25-048-G01 REAMKE
Dillard Rd · G01 REAMKE GLASS
PO TAKA COST
3 notes
  • PO number not recognised: 'TAKA COST'
  • container_dispatch 2026-11-20 differs from batch majority 2026-11-14
  • eta 2026-11-22 differs from batch majority 2026-11-15
AIR 25-048 - Dillard Rd - GP1 Remake - TAKA
fuzzy · 79% · description similarity
2 candidates
Dec 01, 2026 Nov 24, 2026 Nov 30, 2026 → Nov 22, 2026 -8d
TAKA: 2026-11-22 to DALLAS
On track
4d slack
Never Needs review
719 25-206 - - 1MP3
Newman Smith HS Renovation - Stair 14 · FITTINGS
PO 25-206-005
3 notes
  • 2 lines would set this task's ETA: row 701 (2026-11-15), row 719 (2026-11-22). Keep one, discard the rest.
  • container_dispatch 2026-11-20 differs from batch majority 2026-11-14
  • eta 2026-11-22 differs from batch majority 2026-11-15
AIR 25-206 - Newman Smith HS Renovation - Stair 14 - 1MP3 - TAKA
po · 100% · PO 25-206-005
Nov 27, 2026 Nov 20, 2026 Nov 23, 2026 → Nov 22, 2026 -1d
TAKA: 2026-11-22 to DALLAS
On track
0d slack
Never Needs review
720 25-206 - -1IP2
Newman Smith HS Renovation - Stair 14 · WM PANEL
PO 25-206-006
3 notes
  • 2 lines would set this task's ETA: row 702 (2026-11-15), row 720 (2026-11-22). Keep one, discard the rest.
  • container_dispatch 2026-11-20 differs from batch majority 2026-11-14
  • eta 2026-11-22 differs from batch majority 2026-11-15
AIR 25-206 - Newman Smith HS Renovation - Stair 14 -1IP2 - TAKA
po · 100% · PO 25-206-006
Nov 27, 2026 Nov 20, 2026 Nov 23, 2026 → Nov 22, 2026 -1d
TAKA: 2026-11-22 to DALLAS
On track
0d slack
Never Needs review
723 25-120 - - 2MP1
Clemson Veterinary - PHASE 2 · CUBE POST--pc35
PO 25-120-004
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR No task
PO 25-120-004 is on 2 tasks
2 candidates
none → Nov 27, 2026
TAKA: 2026-11-27 to DALLAS
Not assessed Never Needs review
724 25-120 - - 2IP1
Clemson Veterinary - PHASE 2 · WM PANEL--pc35
PO 25-120-007
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR No task
PO 25-120-007 is on 2 tasks
2 candidates
none → Nov 27, 2026
TAKA: 2026-11-27 to DALLAS
Not assessed Never Needs review
725 25-120 - - 2IP2
Clemson Veterinary - PHASE 2 · WM PANEL--pc35
PO 25-120-009
3 notes
  • 2 lines would set this task's ETA: row 707 (2026-11-15), row 725 (2026-11-27). Keep one, discard the rest.
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR 25-120 - Clemson Veterinary - PHASE 2 - 2IP2 - TAKA
po · 100% · PO 25-120-009
Dec 04, 2026 Nov 27, 2026 Nov 23, 2026 → Nov 27, 2026 +4d
TAKA: 2026-11-27 to DALLAS
On track
4d slack
Never Needs review
726 25-120 - - 2MP2
Clemson Veterinary - PHASE 2 · CUBE POST--pc35
PO 25-120-010
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR No task
PO 25-120-010 is on 2 tasks
2 candidates
none → Nov 27, 2026
TAKA: 2026-11-27 to DALLAS
Not assessed Never Needs review
732 26-071 - - Mock Up
Purdue ASB - Perf FOLD · MOCK UP
PO HOLDING
7 notes
  • dispatch date is unrecognised date format (HOLDING)
  • PO number not recognised: 'HOLDING'
  • la_need_by: unrecognised date format ('HOLDING')
  • metal_ready: unrecognised date format ('HOLDING')
  • vessel_loading: unrecognised date format ('HOLDING')
  • container_dispatch: unrecognised date format ('HOLDING')
  • eta: unrecognised date format ('HOLDING')
AIR 26-071 - Purdue ASB - Perf FOLD - Mock Up - TAKA
fuzzy · 100% · description similarity; close runner-up
2 candidates
Nov 27, 2026 Nov 20, 2026 none → HOLDING
TAKA: HOLDING to DALLAS
Not assessed Never Needs review
Batch 79 · no shipment # · ETA to LA
745 26-047- GP1
Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle · bending glass
PO 26-047-003
OCEAN No task
PO 26-047-003 is on 2 tasks
2 candidates
none → Dec 03, 2026
TAKA: 2026-11-19 to LA
Not assessed Never Needs review
Batch 80 · no shipment # · ETA to LA
752 26-088 AML (balance BR192SL-V1)
Eastern Hills · FITTINGS
PO 26-088-004
1 note
  • 2 lines would set this task's ETA: row 656 (2026-11-21), row 752 (2026-12-10). Keep one, discard the rest.
OCEAN 26-088 - Eastern Hills - AML - TAKA
po · 100% · PO 26-088-004
Nov 20, 2026 Nov 06, 2026 Nov 23, 2026 → Dec 10, 2026 +17d
TAKA: 2026-11-26 to LA
At risk: LA + Need By
-20d slack
Never Needs review
753 25-192 GP1
WSVN 7 · NON REFLECTIVE/NON GLARE
PO 25-192-008
OCEAN No task
PO 25-192-008 is on 3 tasks
3 candidates
none → Dec 10, 2026
TAKA: 2026-11-26 to LA
Not assessed Never Needs review
754 25-118 --1MP2
NWISD - PHASE 1 METAL · POST
PO 25-118-013
1 note
  • 2 lines would set this task's ETA: row 699 (2026-11-15), row 754 (2026-12-10). Keep one, discard the rest.
OCEAN 25-118 - NWISD - PHASE 1 - METAL 1MP2 - TAKA
po · 100% · PO 25-118-013
Dec 04, 2026 Nov 20, 2026 Nov 23, 2026 → Dec 10, 2026 +17d
TAKA: 2026-11-26 to LA
At risk: LA + Need By
-6d slack
Never Needs review
755 25-029 - - 3MP1
Richardson · circa multiline post
PO 25-029-009
OCEAN No task
PO 25-029-009 is on 2 tasks
2 candidates
none → Dec 10, 2026
TAKA: 2026-11-26 to LA
Not assessed Never Needs review
760 25-162 - - MP1
North Central Texas College Residence Hall · BLADE POST
PO 25-162-003
2 notes
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN No task
PO 25-162-003 is on 2 tasks
2 candidates
none → Dec 22, 2026
TAKA: 2026-12-08 to LA
Not assessed Never Needs review
763 26-109 Salvation Army
Salvation Army · Salvation Army
PO 26-109-008
2 notes
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN No task
PO 26-109-008 is on 2 tasks
2 candidates
none → Dec 22, 2026
TAKA: 2026-12-08 to LA
Not assessed Never Needs review

Activity

41 lines approved for Wrike (ETA field), with 41 comments · dry run. 589 still need a look and will stay in the exception queue.

Link to a Wrike task