2026 Delivery Schedule Template 2026-10-20.xlsx

Run 5 · uploaded Nov 02, 2026 09:03 AM by VIVA Procurement · sheet "Sheet1 (2)", 80 batches

ready
41will update in Wrike 141need review 448unmatched 69at risk 33 LA · 65 Need By 1waiting on TAKA 47no change

5 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.

Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 37 · SZXLAX67036X · ETA to LA
327 26-022 - - IP1
Telluride School District · zinc primer--MATTE BLACK
PO 26-022-001
1 note
  • metal_ready: unrecognised date format ('recoating, and estimated ready6/17/2026')
OCEAN 26-022 - Telluride School District - IP1- TAKA
po · 100% · PO 26-022-001
Jul 07, 2026 Jun 26, 2026 Aug 07, 2026 → Aug 07, 2026
TAKA: 2026-07-24 to LA
At risk: LA + Need By
-31d slack
Never No change
Batch 40 · SZXCHI67002Y · ETA to DALLAS
357 25-041 GP1 Remake
Jackson Walker · GLASS
PO 25-041-027
1 note
  • new ETA Jul 06, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
po · 100% · PO 25-041-027
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Jul 06, 2026 -94d
TAKA: 2026-07-06 to DALLAS
At risk: Need By
-17d slack
Never Needs review
Batch 47 · SZXLAX68039X · ETA to LA
433 24-075 -- MP5
DFW CTAE · PNAEL FRAME PLATE
PO 24-075-023
1 note
  • new ETA Aug 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 24-075 - DFW CTAE - AREA C4 - EXTERIOR PICKET- IP1 Pending Panel AML -TAKA
po · 100% · PO 24-075-023
Aug 18, 2026 Aug 03, 2026 Sep 10, 2026 → Aug 28, 2026 -13d
TAKA: 2026-08-14 to LA
At risk: LA + Need By
-10d slack
Never Needs review
Batch 50 · SZXCHI68001Y · ETA to DALLAS
457 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Aug 04, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Aug 04, 2026 -65d
TAKA: 2026-08-04 to DALLAS
At risk: Need By
-47d slack
Never Needs review
Batch 52 · SZXLAX68202X · ETA to LA
473 24-075 --Infill Pack 2
DFW CTAE · PNAEL FRAME PLATE
PO 24-075-023
OCEAN 24-075 - DFW CTAE - AREA C4 - EXTERIOR PICKET- IP1 Pending Panel AML -TAKA
po · 100% · PO 24-075-023
Aug 18, 2026 Aug 03, 2026 Sep 10, 2026 → Sep 10, 2026
TAKA: 2026-08-27 to LA
At risk: LA + Need By
-23d slack
Never No change
Batch 58 · SZXLAX69067X · ETA to LA
521 24-075 - IP1
DFW CTAE AREA C4 · 12mm LASER CUT PANEL - PP11--color as sample
PO 24-075-027
2 notes
  • task has no Need By date
  • new ETA Oct 01, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 24-075 - DFW CTAE - AREA C4 (BRIDGES) - IP1 - TAKA- PO APPROVAL
po · 100% · PO 24-075-027
Sep 10, 2026 none → Oct 01, 2026
TAKA: 2026-09-17 to LA
At risk: LA Never Needs review
Batch 59 · SZXCHI69002Y · ETA to DALLAS
531 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Sep 10, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Sep 10, 2026 -28d
TAKA: 2026-09-10 to DALLAS
At risk: Need By
-84d slack
Never Needs review
Batch 60 · SZXLAX69152X · ETA to LA
544 25-125 -- GP1 (except 2pc 25125-G29-V1 & 1pc 25125-G11-V1)
CACC Aviation Hangar · GLASS
PO 25-125-005
1 note
  • new ETA Oct 08, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-125 - CACC Aviation Hangar - GP1 -TAKA
po · 100% · PO 25-125-005
Oct 06, 2026 Sep 22, 2026 Oct 22, 2026 → Oct 08, 2026 -14d
TAKA: 2026-09-24 to LA
At risk: LA + Need By
-2d slack
Never Needs review
Batch 63 · SZXLAX69368X · ETA to LA
573 26-062 - - MP2
TAMU COD · CUBE POST
PO 26-062-003
OCEAN 26-062 - TAMU COD- MP2- TAKA
po · 100% · PO 26-062-003
Oct 21, 2026 Oct 07, 2026 Oct 22, 2026 → Oct 22, 2026
TAKA: 2026-10-08 to LA
At risk: LA + Need By
-1d slack
Never No change
574 25-096 - 3MP1
Cicero North HS Pool · SS316 VIEW BUTTON
PO 25-096-001
OCEAN 25-096 - Cicero North HS Pool - 3MP1 - TAKA
po · 100% · PO 25-096-001
Oct 20, 2026 Sep 30, 2026 Oct 22, 2026 → Oct 22, 2026
TAKA: 2026-10-08 to LA
At risk: LA + Need By
-2d slack
Never No change
580 25-125 GP1 (balance 2pc 25125-G29-V1 & 1pc 25125-G11-V1)
CACC Aviation Hangar · glass
PO 25-125-005
OCEAN 25-125 - CACC Aviation Hangar - GP1 -TAKA
po · 100% · PO 25-125-005
Oct 06, 2026 Sep 22, 2026 Oct 22, 2026 → Oct 22, 2026
TAKA: 2026-10-08 to LA
At risk: LA + Need By
-16d slack
Never No change
Batch 64 · SZXLAX69483X · ETA to LA
582 25-096 3GP1 (balance parts)
Cicero North HS Pool · 21.52pvb glass
PO 25-096-002
1 note
  • new ETA Oct 28, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-096 - Cicero North HS Pool - 3GP1 - TAKA
fuzzy · 100% · job 25-096 + pack 3GP1
2 candidates
Oct 22, 2026 Oct 08, 2026 Oct 22, 2026 → Oct 28, 2026 +6d
TAKA: 2026-10-14 to LA
At risk: LA + Need By
-6d slack
Never Needs review
586 26-046 - MP1
Cobb Galleria · FRAME POST-PPG color
PO 26-046-004
OCEAN 26-046 Cobb Galleria - MP1 - TAKA
container · 97% · job 26-046 + container SZXLAX69483X
Oct 14, 2026 Oct 15, 2026 Oct 28, 2026 → Oct 28, 2026
TAKA: 2026-10-14 to LA
At risk: Need By
-14d slack
Never No change
587 26-046 - IP1 (part of materails)
Cobb Galleria · ALU PANEL-PPG color
PO 26-046-005
OCEAN 26-046 Cobb Galleria - IP1 - TAKA
po · 100% · PO 26-046-005
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Oct 28, 2026
TAKA: 2026-10-14 to LA
At risk: LA + Need By
-13d slack
Never No change
589 25-085 - - MP3
ARC - METAL SPACES · FOLD frame--PC23 black
PO 25-085-009
OCEAN 25-085 - ARC - METAL SPACES - MP3 - TAKA
po · 100% · PO 25-085-009
Oct 27, 2026 Oct 13, 2026 Oct 28, 2026 → Oct 28, 2026
TAKA: 2026-10-14 to LA
At risk: LA + Need By
-1d slack
Never No change
590 25-085 - -IP3
ARC - METAL SPACES · FOLD frame-PC23 black
PO 25-085-008
OCEAN 25-085 - ARC - METAL SPACES - IP3- TAKA
po · 100% · PO 25-085-008
Oct 27, 2026 Oct 13, 2026 Oct 28, 2026 → Oct 28, 2026
TAKA: 2026-10-14 to LA
At risk: LA + Need By
-1d slack
Never No change
Batch 67 · SZXLAX6A088X · ETA to LA
605 25-203 - - MP1 (balance PB105FL)
J Marshall HS · FOLD POST
PO NA
OCEAN 25-203 - J Marshall HS - MP1 - TAKA
fuzzy · 100% · job 25-203 + pack MP1
Nov 11, 2026 Oct 20, 2026 Nov 04, 2026 → Nov 04, 2026
TAKA: 2026-10-21 to LA
At risk: LA
7d slack
Never No change
606 26-046 - IP1 (balance part of materails)
Cobb Galleria · ALU PANEL-PPG color
PO 26-046-005
OCEAN 26-046 Cobb Galleria - IP1 - TAKA
po · 100% · PO 26-046-005
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Nov 04, 2026 +7d
TAKA: 2026-10-21 to LA
At risk: LA + Need By
-20d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-046 - IP1 (balance part of materails)
New ETA to warehouse: Nov 04, 2026 (was Oct 28, 2026, +7 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-21, shipment SZXLAX6A088X
Risk: At risk for both the LA Need By and Need By dates (-20 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 606. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
608 25-145- IP1 (part of panels)
Kingsport Library · ALUMINUM FRAMED PANEL--PC22
PO 25-145-002
OCEAN 25-145 Kingsport Library - IP1 - TAKA
po · 100% · PO 25-145-002
Oct 30, 2026 Oct 16, 2026 Nov 04, 2026 → Nov 04, 2026
TAKA: 2026-10-21 to LA
At risk: LA + Need By
-5d slack
Never No change
Batch 71 · SZXLAX6A132X · ETA to LA
629 26-019 - - GP1 (balance 1 case glass)
United Regional · GLASS
PO 26-019-003
OCEAN 26-019 - United Regional - GP1 -TAKA
po · 100% · PO 26-019-003
Nov 06, 2026 Oct 30, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-019 - GP1 (balance 1 case glass)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for the Need By date (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 629. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
630 26-028 MP1 (balance EP220BC)
Sapulpa High School · BEACON POST
PO 26-028-005
OCEAN 26-028 - Sapulpa High School - MP1 - TAKA
po · 100% · PO 26-028-005
Nov 06, 2026 Oct 23, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: LA + Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-028 MP1 (balance EP220BC)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for both the LA Need By and Need By dates (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 630. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
631 25-145- IP1 (balance of panels)
Kingsport Library · ALUMINUM FRAMED PANEL--PC22
PO 25-145-002
OCEAN 25-145 Kingsport Library - IP1 - TAKA
po · 100% · PO 25-145-002
Oct 30, 2026 Oct 16, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: LA + Need By
-11d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-145- IP1 (balance of panels)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for both the LA Need By and Need By dates (-11 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 631. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
634 25-209 - - IP1
WALTON SCHOOL · ALU FOLD PANEL--PC54
PO 25-209-001
OCEAN 25-209 - WALTON SCHOOL - IP1 - TAKA
po · 100% · PO 25-209-001
Nov 06, 2026 Oct 23, 2026 Nov 10, 2026 → Nov 10, 2026
TAKA: 2026-10-27 to LA
At risk: LA + Need By
-4d slack
Never No change
635 25-209 - - MP1 (excetp 25209-CN01--2EA )
WALTON SCHOOL · FOLD POST
PO 25-209-002
OCEAN 25-209 - WALTON SCHOOL - MP1 - TAKA
po · 100% · PO 25-209-002
Nov 09, 2026 Oct 30, 2026 Nov 10, 2026 → Nov 10, 2026
TAKA: 2026-10-27 to LA
At risk: Need By
-1d slack
Never No change
641 25-181 - - MP1
First & Market · BLADE POST and gate
PO 25-181-003
OCEAN 25-181 - First & Market - MP1 - TAKA
po · 100% · PO 25-181-003
Nov 09, 2026 Oct 30, 2026 Nov 10, 2026 → Nov 10, 2026
TAKA: 2026-10-27 to LA
At risk: Need By
-1d slack
Never No change
Batch 72 · SZXCHI6A003Y · ETA to DALLAS
643 26-127 Mock Up
Gainesville PD · Mock Up ---RAL5022
PO 26-127-001
1 note
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-127 - Gainesville PD - Mock Up - TAKA
po · 100% · PO 26-127-001
Oct 08, 2026 Sep 30, 2026 Oct 22, 2026 → Oct 15, 2026 -7d
TAKA: 2026-10-15 to DALLAS
At risk: Need By
-13d slack
Never Needs review
645 25-041- GP1
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Oct 15, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 90% · job 25-041 + pack GP1
2 candidates
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Oct 15, 2026 +7d
TAKA: 2026-10-15 to DALLAS
At risk: Need By
-119d slack
Never Needs review
Batch 73 · SZXLAX6A235X · ETA to LA
652 26-028 - GP1
Sapulpa High School · GLASS
PO 26-028-003
OCEAN 26-028 - Sapulpa High School - GP1 - TAKA
po · 100% · PO 26-028-003
Nov 06, 2026 Oct 30, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
At risk: LA + Need By
-15d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-028 - GP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: At risk for both the LA Need By and Need By dates (-15 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 652. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
656 26-088 AML (Sent 3" SQ.TUBE firstly)
Eastern Hills · FITTINGS
PO 26-088-004
1 note
  • 2 lines would set this task's ETA: row 656 (2026-11-21), row 752 (2026-12-10). Keep one, discard the rest.
OCEAN 26-088 - Eastern Hills - AML - TAKA
po · 100% · PO 26-088-004
Nov 20, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
At risk: LA + Need By
-1d slack
Never Needs review
Batch 74 · flight booked · ETA to DALLAS
663 26-076 -- Mock Up (only glass)
Prairie SS Center - Blade GLASS · Blade Glass - Mock Up
PO 26-076-001
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-076 - Prairie SS Center - Blade Glass - Mock Up - TAKA
po · 100% · PO 26-076-001
Oct 23, 2026 Oct 16, 2026 Oct 22, 2026 → Oct 25, 2026 +3d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-8d slack
Never Needs review
667 26-102 -- Mock Up
Natatorium NR Dining · SHOE MOCK UP
PO 26-102-004
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-102 - Natatorium NR Dining - Mock Up - SHOE - TAKA
po · 100% · PO 26-102-004
Oct 23, 2026 Oct 16, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-8d slack
Never Needs review
669 26-058 - Mock Up
UAH - · beacon mock up
PO 26-058-001
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-058 - UAH - Mock Up - TAKA
po · 100% · PO 26-058-001
Oct 30, 2026 Oct 23, 2026 Nov 09, 2026 → Oct 25, 2026 -15d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-1d slack
Never Needs review
670 24-200 - - 2MP3
North Carolina Education Campus · CONNECTOR
PO 24-200-019
1 note
  • new ETA Oct 25, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 24-200 - North Carolina Education Campus - 2MP3 - TAKA
po · 100% · PO 24-200-019
Oct 30, 2026 Oct 23, 2026 Nov 02, 2026 → Oct 25, 2026 -8d
TAKA: 2026-10-25 to DALLAS
At risk: Need By
-1d slack
Never Needs review
Batch 75 · no shipment # · ETA to DALLAS
676 25-075 - - IP2 remakes
UM Gem Factory · Cablenet PANEL
PO 25-075-007
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-075 - UM Gem Factory - IP2 remakes - TAKA
po · 100% · PO 25-075-007
Oct 23, 2026 Oct 16, 2026 Nov 02, 2026 → Oct 30, 2026 -3d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-10d slack
Never Needs review
677 26-079 MOCK UP
Old Mill · BLADE WM15
PO 26-079-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-079 - Old Mill - Mock Up - Blade WM - TAKA
po · 100% · PO 26-079-001
Oct 30, 2026 Oct 23, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-3d slack
Never Needs review
678 26-209 - MOCK-UP and color sample
JH Carter -Benjamin Moore 2062-10 SAMP · 8mm x 50mm flat bar mock up
PO 26-209-001
1 note
  • new ETA Oct 30, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 26-209 - JH Carter -Benjamin Moore 2062-10 SAMP - TAKA
po · 100% · PO 26-209-001
Oct 20, 2026 Oct 13, 2026 Nov 09, 2026 → Oct 30, 2026 -10d
TAKA: 2026-10-30 to DALLAS
At risk: Need By
-13d slack
Never Needs review
Batch 76 · no shipment # · ETA to DALLAS
689 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Nov 08, 2026 +31d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-143d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-041 - GP1 Remake G09
New ETA to warehouse: Nov 08, 2026 (was Oct 08, 2026, +31 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-143 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 689. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
690 25-038 - - G08
East Dallas · G08 GLASS
PO 25-038-013
1 note
  • order_date: unrecognised date format ('101/2026')
AIR 25-038 - East Dallas - G08 - TAKA
po · 100% · PO 25-038-013
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-038 - G08
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 690. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
691 24-040 -- 2IP4
Project Meadow - Level 8 Picket · ALU PICKET PANEL
PO 24-040-046
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow - Level 8 Picket- 2IP4 - TAKA
po · 100% · PO 24-040-046
Nov 13, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
692 24-040 -- - 2MP6
Project Meadow - Level 8 Picket · FITTINGS
PO 24-040-045
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow - Level 8 Picket- 2MP6 - TAKA
po · 100% · PO 24-040-045
Nov 13, 2026 Nov 06, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
693 24-040 - -2MP7
Project Meadow · FITTINGS
PO 24-040-052
1 note
  • would move the ETA 15 days earlier than Wrike holds (Nov 23, 2026); check this is TAKA's latest schedule
AIR 24-040 - Project Meadow -2MP7 - TAKA
po · 100% · PO 24-040-052
Nov 13, 2026 Nov 10, 2026 Nov 23, 2026 → Nov 08, 2026 -15d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Needs review
694 25-049 -- SW7006 - SAMP
Redding Rancheria · SW 7006 COLOR SAMPLE
PO 25-049-003
AIR 25-049 - Redding Rancheria - SW7006 - SAMP - TAKA
po · 100% · PO 25-049-003
Nov 13, 2026 Nov 06, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-049 - SW7006 - SAMP
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 694. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
695 25-211 SW9062 color sample
25-211 SW9062 · SW9062 COLOR SAMPLE
PO 25-211-002
AIR 25-211 - Deanna Davenport Elementary School -SW 9062 - TAKA
po · 100% · PO 25-211-002
Nov 13, 2026 Nov 06, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-211 SW9062 color sample
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 695. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
696 26-078 -- SM10253 & 379A1455
Klein Tools · 2 COLOR SAMPLE
PO 26-078-002
AIR 26-078 - Klein Tools - KAWNEER 379A1455 Permadize Champagne & SM10253 SAMP - TAKA
po · 100% · PO 26-078-002
Nov 06, 2026 Oct 30, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-8d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-078 - SM10253 & 379A1455
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-8 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 696. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
697 24-075 - Infill Pack 2 Remake
DFW CTAE - · INFILL PANEL Remakes
PO NA
AIR 24-075 - DFW CTAE - Infill Pack 2 Remake - TAKA
fuzzy · 100% · job 24-075 + pack IP2
Oct 30, 2026 Oct 23, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-15d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-075 - Infill Pack 2 Remake
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment TAKA COST
Risk: At risk for the Need By date (-15 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 697. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 77 · no shipment # · ETA to DALLAS
703 26-084 - - MP2
THR Midlothian · VORTEX POST
PO 26-084-002
AIR 26-084 - THR Midlothian - MP2 - TAKA
po · 100% · PO 26-084-002
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-084 - MP2
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 703. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
705 25-120 - - 1MP2
Clemson Veterinary(HUB BUILDING) · CUBE POST--pc35
PO 25-120-004
AIR 25-120 - Clemson Veterinary(HUB BUILDING)- 1MP2 - TAKA
po · 98% · PO 25-120-004 + pack 1MP2
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-120 - 1MP2
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 705. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
706 25-120 - - 1IP1
Clemson Veterinary(HUB BUILDING) · WM PANEL--pc35
PO 25-120-006
AIR 25-120 - Clemson Veterinary(HUB BUILDING)- 1IP1 - TAKA
po · 100% · PO 25-120-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-120 - 1IP1
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 706. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
708 26-202 - - MOCK UP
TALLAHASSEE POLICE HEADQUARTERS - Florida · Mock Up --RAL5011
PO 26-202-001
AIR 26-202 - TALLAHASSEE POLICE HEADQUARTERS - Florida - MOCK UP- TAKA
po · 100% · PO 26-202-001
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-202 - MOCK UP
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 708. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
711 25-136 - - IP4
Roy & Helen Hunt Library Renovation · ALU PANEL
PO 25-136-005
AIR 25-136 - Roy & Helen Hunt Library Renovation - IP4 - TAKA
po · 100% · PO 25-136-005
Nov 19, 2026 Nov 12, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-2d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-136 - IP4
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-2 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 711. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
712 25-030 -- MP3
TAMU CC · FITITNGS
PO 25-030-006
AIR 25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-030 - MP3
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 712. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
713 25-033 -MP1 (Missing Materials)
East Montgomery - Stair 6 Remakes · FITITNGS
PO 25-033-025
AIR 25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
po · 100% · PO 25-033-025
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Nov 15, 2026 -1d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-033 -MP1 (Missing Materials)
New ETA to warehouse: Nov 15, 2026 (was Nov 16, 2026, -1 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 713. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
714 25-030 - - MP3
TAMU CC · FITITNGS
PO 25-030-006
AIR 25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-030 - MP3
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 714. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
721 25-115 - - IP2
Garden City · WIRE mesh panel-- PC36
PO 25-115-008
2 notes
  • container_dispatch 2026-11-20 differs from batch majority 2026-11-14
  • eta 2026-11-22 differs from batch majority 2026-11-15
AIR 25-115 - Garden City - IP2 - TAKA
po · 100% · PO 25-115-008
Nov 26, 2026 Nov 19, 2026 Nov 30, 2026 → Nov 22, 2026 -8d
TAKA: 2026-11-22 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-115 - IP2
New ETA to warehouse: Nov 22, 2026 (was Nov 30, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-22, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 721. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
729 24-040 - - - MP5 Remake
Project Meadow - LVL 2 1CL01 Cladding 10nosCL01 · CLADDING
PO 24-040-053
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR 24-040 - Project Meadow - LVL 2 - 1CL01 Cladding 10nosCL01 - MP5 Remake - TAKA
po · 100% · PO 24-040-053
Nov 27, 2026 Dec 21, 2026 Dec 04, 2026 → Nov 27, 2026 -7d
TAKA: 2026-11-27 to DALLAS
At risk: Need By
-3d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-040 - MP5 Remake
New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet
Risk: At risk for the Need By date (-3 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 729. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 78 · vessel booked · ETA to LA
736 25-209 - - MP1 (balance 25209-CN01--2EA )
WALTON SCHOOL · FOLD POST
PO 25-209-002
OCEAN 25-209 - WALTON SCHOOL - MP1 - TAKA
po · 100% · PO 25-209-002
Nov 09, 2026 Oct 30, 2026 Nov 10, 2026 → Nov 27, 2026 +17d
TAKA: 2026-11-13 to LA
At risk: LA + Need By
-18d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-209 - MP1 (balance 25209-CN01 - 2EA )
New ETA to warehouse: Nov 27, 2026 (was Nov 10, 2026, +17 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-13, shipment vessel booked
Risk: At risk for both the LA Need By and Need By dates (-18 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 736. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
737 25-204 - MP1 (balance materials)
QTS DFW2-DC4 - Lobby Stair & Opening · SS316 U CAP FITTINGS
PO 25-204-003
OCEAN 25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - MP1 - TAKA
po · 100% · PO 25-204-003
Nov 24, 2026 Nov 10, 2026 Nov 27, 2026 → Nov 27, 2026
TAKA: 2026-11-13 to LA
At risk: LA + Need By
-3d slack
Never No change
740 25-114 Infill Pack 1
Crowley · perforated panel
PO 25-114-002
OCEAN 25-114 - Crowley - IP1 - TAKA
po · 100% · PO 25-114-002
Nov 13, 2026 Nov 20, 2026 Nov 27, 2026 → Nov 27, 2026
TAKA: 2026-11-13 to LA
At risk: Need By
-14d slack
Never No change
741 25-204 GP1
QTS DFW2-DC4 · glass
PO 25-204-001
OCEAN 25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - GP1 - TAKA
po · 100% · PO 25-204-001
Nov 23, 2026 Nov 09, 2026 Nov 27, 2026 → Nov 27, 2026
TAKA: 2026-11-13 to LA
At risk: LA + Need By
-4d slack
Never No change
742 26-149 - 22 Post FOLD PANEL
Richardson ISD - · POST
PO 26-149-001
OCEAN 26-149 - Richardson ISD - 22 Post FOLD PANEL - TAKA
po · 100% · PO 26-149-001
Nov 06, 2026 Oct 23, 2026 Nov 27, 2026 → Nov 27, 2026
TAKA: 2026-11-13 to LA
At risk: LA + Need By
-21d slack
Never No change
Batch 79 · no shipment # · ETA to LA
746 26-089 - - IP1
SUNY Morrisville · 6MM ALU PANEL
PO 26-089-003
OCEAN 26-089 - SUNY Morrisville - IP1 - TAKA
po · 100% · PO 26-089-003
Dec 01, 2026 Nov 17, 2026 Dec 03, 2026 → Dec 03, 2026
TAKA: 2026-11-19 to LA
At risk: LA + Need By
-2d slack
Never No change
747 25-029 - 2GP2
Richardson · GLASS
PO 25-029-008
OCEAN 25-029 - Richardson - 2GP2 -TAKA
po · 100% · PO 25-029-008
Dec 01, 2026 Nov 17, 2026 Dec 03, 2026 → Dec 03, 2026
TAKA: 2026-11-19 to LA
At risk: LA + Need By
-2d slack
Never No change
748 25-006 - -IP1
Forest Oaks · ALU PANEL--PC27
PO 25-006-001
OCEAN 25-006 - Forest Oaks - IP1 - TAKA
po · 100% · PO 25-006-001
Dec 02, 2026 Nov 18, 2026 Nov 16, 2026 → Dec 03, 2026 +17d
TAKA: 2026-11-19 to LA
At risk: LA + Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-006 - IP1
New ETA to warehouse: Dec 03, 2026 (was Nov 16, 2026, +17 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-19, shipment not assigned yet
Risk: At risk for both the LA Need By and Need By dates (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 748. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
749 25-006 - - MP1
Forest Oaks · STRUC POST--PC27
PO 25-006-002
OCEAN 25-006 - Forest Oaks - MP1 - TAKA
po · 100% · PO 25-006-002
Nov 04, 2026 Oct 22, 2026 Dec 03, 2026 → Dec 03, 2026
TAKA: 2026-11-19 to LA
At risk: LA + Need By
-29d slack
Never No change
750 26-024 - MP1
Regeneron Building · FITTING AND PICKET PANEL
PO 26-024-003
OCEAN 26-024 - Regeneron Building MP1 - TAKA
po · 100% · PO 26-024-003
Dec 04, 2026 Oct 23, 2026 Dec 03, 2026 → Dec 03, 2026
TAKA: 2026-11-19 to LA
At risk: LA
1d slack
Never No change
Batch 80 · no shipment # · ETA to LA
752 26-088 AML (balance BR192SL-V1)
Eastern Hills · FITTINGS
PO 26-088-004
1 note
  • 2 lines would set this task's ETA: row 656 (2026-11-21), row 752 (2026-12-10). Keep one, discard the rest.
OCEAN 26-088 - Eastern Hills - AML - TAKA
po · 100% · PO 26-088-004
Nov 20, 2026 Nov 06, 2026 Nov 23, 2026 → Dec 10, 2026 +17d
TAKA: 2026-11-26 to LA
At risk: LA + Need By
-20d slack
Never Needs review
754 25-118 --1MP2
NWISD - PHASE 1 METAL · POST
PO 25-118-013
1 note
  • 2 lines would set this task's ETA: row 699 (2026-11-15), row 754 (2026-12-10). Keep one, discard the rest.
OCEAN 25-118 - NWISD - PHASE 1 - METAL 1MP2 - TAKA
po · 100% · PO 25-118-013
Dec 04, 2026 Nov 20, 2026 Nov 23, 2026 → Dec 10, 2026 +17d
TAKA: 2026-11-26 to LA
At risk: LA + Need By
-6d slack
Never Needs review
761 25-049 - - IP1
Redding Rancheria · STRUC PANEL SOLID 12MM--MC73
PO 25-049-006
2 notes
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN 25-049 - Redding Rancheria - IP1 - TAKA
po · 100% · PO 25-049-006
Dec 18, 2026 Dec 04, 2026 Dec 22, 2026 → Dec 22, 2026
TAKA: 2026-12-08 to LA
At risk: LA + Need By
-4d slack
Never No change
762 25-049 - - MP1
Redding Rancheria · STRUC POST--MC73
PO 25-049-007
3 notes
  • task has no Need By date
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN 25-049 - Redding Rancheria - MP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 25-049 + pack MP1
Dec 04, 2026 none → Dec 22, 2026
TAKA: 2026-12-08 to LA
At risk: LA Never Will write
Wrike comment preview
TAKA ETA update for 25-049 - MP1
New ETA to warehouse: Dec 22, 2026 (first ETA from TAKA)
TAKA schedule: OCEAN, ETA to LA 2026-12-08, shipment not assigned yet
Risk: At risk for the LA Need By date
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 762. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.

Activity

41 lines approved for Wrike (ETA field), with 41 comments · dry run. 589 still need a look and will stay in the exception queue.

Link to a Wrike task