TAKA orders at a glance
Live from Wrike, read Nov 03, 2026 12:35 PM · refreshes every 30 min · read-only
Open TAKA orders
223
$765,970 PO value
At risk vs Need By
44
20% of open orders, not yet received
Arriving in 14 days
39
83 within 30 days
ETA passed, not received
10
chase TAKA or close the task
No ETA to warehouse68
No Need By date66
TAKA ETA slipn/aafter the first approved upload with prior ETAs
Schedule freshnessnone yetlast upload Nov 02, not yet approved
Where open orders are
by Wrike status, groupedAt TAKA and Shipping are the stages a schedule upload can move.
Arrivals at the warehouse, next 6 weeks
OceanAirOtherShow as table
| Week of | Ocean | Air | Other |
|---|---|---|---|
| Nov 02, 2026 | 7 | 12 | 0 |
| Nov 09, 2026 | 7 | 11 | 0 |
| Nov 16, 2026 | 2 | 10 | 2 |
| Nov 23, 2026 | 13 | 22 | 0 |
| Nov 30, 2026 | 5 | 12 | 0 |
| Dec 07, 2026 | 7 | 0 | 0 |
On time vs Need By
received, last 90 daysOcean54%
57 received · target 85% (tick)
Air73%
62 received · target 75% (tick)
PM workload
At riskOther openTop 10 by open orders. Click a name for their list.
Needs a person
Exceptions (12)
- 24-120-10 - TAMIUError Assigned to Department
- 25-050 - Cheshire Elementary School - Infill Pack 1 - Remake panelsQC Rejected
- 25-107 - CommonwealthError Assigned to Department
- 25-057-10 - Montage at MidtownError Assigned to Department
- 24-201 - McDanielError Assigned to Department
- Boxes for samples (Sales) - TAKAOrder on Hold
- 26-022 - Telluride School District - IP1- TAKAQC Rejected
- 25-143 - HCA LSMC - Replacement Stock Order - TAKAOrder on Hold
At-risk orders: ETA after Need By, not yet received
See all 44| Wrike task | Stage | Mode | PM | Need By | ETA to WH | Days late | LA Need by | Container | PO value | Risk (Wrike) | PM last notified |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 26-183 - First Baptist Church Garland - SW7695- SAMP - TAKA | Exceptions Order on Hold |
AIR | Charlie | Sep 11, 2026 | Oct 30, 2026 | +49 | Sep 04, 2026 | DELAYED |
Never | ||
| 26-149 - Richardson ISD - 22 Post FOLD PANEL - TAKA | Shipping In Transit |
OCEAN | Alfredo | Nov 06, 2026 | Nov 27, 2026 | +21 | Oct 23, 2026 | SZXLAX6A335X | $542 | 3. At Risk DELAYED |
Never |
| 26-028 - Sapulpa High School - GP1 - TAKA | Shipping In Transit |
OCEAN | Reza Maheri | Nov 06, 2026 | Nov 23, 2026 | +17 | Oct 30, 2026 | SZXLAX6A235X | $5,868 | 3. At Risk DELAYED |
Never |
| 24-075 - DFW CTAE - Infill Pack 2 Remake - TAKA | Shipping In Transit |
AIR | Victor | Oct 30, 2026 | Nov 16, 2026 | +17 | Oct 23, 2026 | 3. At Risk DELAYED |
Never | ||
| 26-127 - Gainesville PD - Mock Up - TAKA | Quote and approval PM Approval Needed |
AIR | MO | Oct 08, 2026 | Oct 22, 2026 | +14 | Sep 30, 2026 | $249 | 3. At Risk DELAYED |
Never | |
| 25-114 - Crowley - IP1 - TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Nov 13, 2026 | Nov 27, 2026 | +14 | Nov 20, 2026 | SZXLAX6A335X | $4,708 | 3. At Risk DELAYED |
Never |
| 24-040 - Project Meadow - Level 8 Picket- 2IP4 - TAKA | At TAKA In Works / AT vendor |
AIR | Alfredo | Nov 13, 2026 | Nov 23, 2026 | +10 | Nov 06, 2026 | $780 | 3. At Risk | Never | |
| 24-040 - Project Meadow - Additional Glass Scope L10- 1MP6 - TAKA | Shipping In Transit |
AIR | Alfredo | Nov 13, 2026 | Nov 23, 2026 | +10 | Nov 06, 2026 | $122 | 3. At Risk DELAYED |
Never | |
| 25-062 - RDNI - IP3- TAKA | Shipping In Transit |
AIR | Coleby | Nov 06, 2026 | Nov 16, 2026 | +10 | Oct 30, 2026 | $106 | 3. At Risk DELAYED |
Never | |
| 25-033 - East Montgomery - Stair 06 Handrails - MP4- TAKA | Shipping In Transit |
AIR | Charlie | Nov 06, 2026 | Nov 16, 2026 | +10 | Oct 30, 2026 | $4,434 | 3. At Risk DELAYED |
Never | |
| 24-040 - Project Meadow -2MP7 - TAKA | At TAKA In Works / AT vendor |
AIR | Alfredo | Nov 13, 2026 | Nov 23, 2026 | +10 | Nov 10, 2026 | $77 | 3. At Risk | Never | |
| 24-040 - Project Meadow - Level 8 Picket- 2MP6 - TAKA | At TAKA In Works / AT vendor |
AIR | Alfredo | Nov 13, 2026 | Nov 23, 2026 | +10 | Nov 06, 2026 | $13 | 3. At Risk | Never | |
| 26-078 - Klein Tools - KAWNEER 379A1455 Permadize Champagne & SM10253 SAMP - TAKA | At TAKA In Works / AT vendor |
Reza Maheri | Nov 06, 2026 | Nov 16, 2026 | +10 | Oct 30, 2026 | $262 | 3. At Risk DELAYED |
Never | ||
| 26-079 - Old Mill - Mock Up - Blade WM - TAKA | Quote and approval PM Approval Needed |
AIR | Alfredo | Oct 30, 2026 | Nov 09, 2026 | +10 | Oct 23, 2026 | 26-079-001 | $410 | 3. At Risk DELAYED |
Never |
| 24-040 - Project Meadow - LVL 2 - 1CL01 Cladding 10nosCL01 - MP5 Remake - TAKA | At TAKA In Works / AT vendor |
AIR | Alfredo | Nov 27, 2026 | Dec 04, 2026 | +7 | Dec 21, 2026 | $275 | 1. On Track | Never |