← All uploads
ready
2026 Delivery Schedule Template 2026-10-20.xlsx
Run 5 · uploaded Nov 02, 2026 09:03 AM by VIVA Procurement · sheet "Sheet1 (2)", 80 batches
5 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.
| Row | Schedule line | Mode | Wrike task | Need By | LA Need By | Prior ETA → New ETA | Risk | PM last notified | Decision |
|---|---|---|---|---|---|---|---|---|---|
| Batch 67 · SZXLAX6A088X · ETA to LA | |||||||||
| 606 |
26-046 - IP1 (balance part of materails)
Cobb Galleria · ALU PANEL-PPG color
PO 26-046-005
|
OCEAN |
26-046 Cobb Galleria - IP1 - TAKA
po · 100% · PO 26-046-005
|
Oct 15, 2026 | Oct 01, 2026 |
Oct 28, 2026 → Nov 04, 2026
+7d
TAKA: 2026-10-21 to LA
|
At risk: LA + Need By
-20d slack |
Never |
Will write
|
| Batch 71 · SZXLAX6A132X · ETA to LA | |||||||||
| 629 |
26-019 - - GP1 (balance 1 case glass)
United Regional · GLASS
PO 26-019-003
|
OCEAN |
26-019 - United Regional - GP1 -TAKA
po · 100% · PO 26-019-003
|
Nov 06, 2026 | Oct 30, 2026 |
Nov 04, 2026 → Nov 10, 2026
+6d
TAKA: 2026-10-27 to LA
|
At risk: Need By
-4d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-019 - GP1 (balance 1 case glass) New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days) TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X Risk: At risk for the Need By date (-4 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 629. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 630 |
26-028 MP1 (balance EP220BC)
Sapulpa High School · BEACON POST
PO 26-028-005
|
OCEAN |
26-028 - Sapulpa High School - MP1 - TAKA
po · 100% · PO 26-028-005
|
Nov 06, 2026 | Oct 23, 2026 |
Nov 04, 2026 → Nov 10, 2026
+6d
TAKA: 2026-10-27 to LA
|
At risk: LA + Need By
-4d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-028 MP1 (balance EP220BC) New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days) TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X Risk: At risk for both the LA Need By and Need By dates (-4 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 630. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 631 |
25-145- IP1 (balance of panels)
Kingsport Library · ALUMINUM FRAMED PANEL--PC22
PO 25-145-002
|
OCEAN |
25-145 Kingsport Library - IP1 - TAKA
po · 100% · PO 25-145-002
|
Oct 30, 2026 | Oct 16, 2026 |
Nov 04, 2026 → Nov 10, 2026
+6d
TAKA: 2026-10-27 to LA
|
At risk: LA + Need By
-11d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-145- IP1 (balance of panels) New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days) TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X Risk: At risk for both the LA Need By and Need By dates (-11 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 631. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 632 |
TSC-ST26032 Color Chip Samples
Color Chip Samples · Color Chip Samples
PO VS2026-031
2 notes
|
OCEAN |
Taka Order - Color Chip Samples - 8-10-2026
po · 100% · PO VS2026-031
|
Oct 28, 2026 → Nov 10, 2026
+13d
TAKA: 2026-10-27 to LA
|
Not assessed | Never |
Will write
Wrike comment previewTAKA ETA update for TSC-ST26032 Color Chip Samples New ETA to warehouse: Nov 10, 2026 (was Oct 28, 2026, +13 days) TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X Risk: Not assessed (a date is missing) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 632. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
||
| Batch 73 · SZXLAX6A235X · ETA to LA | |||||||||
| 652 |
26-028 - GP1
Sapulpa High School · GLASS
PO 26-028-003
|
OCEAN |
26-028 - Sapulpa High School - GP1 - TAKA
po · 100% · PO 26-028-003
|
Nov 06, 2026 | Oct 30, 2026 |
Nov 23, 2026 → Nov 21, 2026
-2d
TAKA: 2026-11-07 to LA
|
At risk: LA + Need By
-15d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-028 - GP1 New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: At risk for both the LA Need By and Need By dates (-15 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 652. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 653 |
25-206 IP1
Newman Smith HS - Stair 4 · wire mesh panel
PO 25-206-003
|
OCEAN |
25-206 - Newman Smith HS - Stair 4 Only - IP1-TAKA
po · 100% · PO 25-206-003
|
Nov 24, 2026 | Nov 10, 2026 |
Nov 23, 2026 → Nov 21, 2026
-2d
TAKA: 2026-11-07 to LA
|
On track
3d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-206 IP1 New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track (3 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 653. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 655 |
25-204 - MP1 (except CR121DC)
QTS DFW2-DC4 - Lobby Stair & Opening · SS316 U CAP FITTINGS
PO 25-204-003
|
OCEAN |
25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - MP1 - TAKA
po · 100% · PO 25-204-003
|
Nov 24, 2026 | Nov 10, 2026 |
Nov 27, 2026 → Nov 21, 2026
-6d
TAKA: 2026-11-07 to LA
|
On track
3d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-204 - MP1 (except CR121DC) New ETA to warehouse: Nov 21, 2026 (was Nov 27, 2026, -6 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track (3 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 655. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 657 |
25-029 - - 2MP1
Richardson · SOLO POST
PO 25-029-007
1 note
|
OCEAN |
25-029 - Richardson - 2MP1 - TAKA- PO APPROVAL
po · 100% · PO 25-029-007
|
Nov 09, 2026 |
none → Nov 21, 2026
TAKA: 2026-11-07 to LA
|
On track | Never |
Will write
Wrike comment previewTAKA ETA update for 25-029 - 2MP1 New ETA to warehouse: Nov 21, 2026 (first ETA from TAKA) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 657. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
|
| 658 |
25-029 - MP1
Richardson · FSR POST
PO 25-029-006
|
OCEAN |
25-029 - Richardson - MP1 - TAKA
po · 100% · PO 25-029-006
|
Nov 30, 2026 | Nov 09, 2026 |
Nov 23, 2026 → Nov 21, 2026
-2d
TAKA: 2026-11-07 to LA
|
On track
9d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-029 - MP1 New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track (9 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 658. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 659 |
26-163 - - IP1
Publix #2111 - Lake Hills · PICKET PANEL
PO 26-163-001
|
OCEAN |
26-163 - Publix #2111 - Lake Hills - IP1 - TAKA
po · 100% · PO 26-163-001
|
Dec 08, 2026 | Nov 24, 2026 |
Nov 23, 2026 → Nov 21, 2026
-2d
TAKA: 2026-11-07 to LA
|
On track
17d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-163 - IP1 New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track (17 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 659. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 660 |
26-163 - - MP1
Publix #2111 - Lake Hills · POST
PO 26-163-002
|
OCEAN |
26-163 - Publix #2111 - Lake Hills - MP1 - TAKA
po · 100% · PO 26-163-002
|
Dec 08, 2026 | Nov 24, 2026 |
Nov 23, 2026 → Nov 21, 2026
-2d
TAKA: 2026-11-07 to LA
|
On track
17d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-163 - MP1 New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days) TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X Risk: On track (17 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 660. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 75 · no shipment # · ETA to DALLAS | |||||||||
| 685 |
25-076 - - 25076-1IP32R REMAKE
Norton ES - IP4 Remake - TAKA · 25076-1IP32R remake
PO TAKA COST
4 notes
|
AIR |
25-076 - Norton ES - IP4 Remake - TAKA
fuzzy · 100% · job 25-076 + pack IP4
|
Oct 20, 2026 |
Nov 02, 2026 → Nov 03, 2026
+1d
TAKA: 2026-11-03 to DALLAS
|
Not assessed | Never |
Will write
Wrike comment previewTAKA ETA update for 25-076 - 25076-1IP32R REMAKE New ETA to warehouse: Nov 03, 2026 (was Nov 02, 2026, +1 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-03, shipment not assigned yet Risk: Not assessed (a date is missing) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 685. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
|
| 686 |
26-115 - MP1
Phoenix Zoo Veterinary Medical Center · CONNECTOR
PO 26-115-002
2 notes
|
AIR |
26-115 - Phoenix Zoo Veterinary Medical Center MP1 - TAKA
po · 100% · PO 26-115-002
|
Nov 13, 2026 | Nov 06, 2026 |
Nov 06, 2026 → Nov 03, 2026
-3d
TAKA: 2026-11-03 to DALLAS
|
On track
6d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-115 - MP1 New ETA to warehouse: Nov 03, 2026 (was Nov 06, 2026, -3 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-03, shipment not assigned yet Risk: On track (6 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 686. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 76 · no shipment # · ETA to DALLAS | |||||||||
| 689 |
25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
|
AIR |
25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
|
Jun 24, 2026 | Jun 17, 2026 |
Oct 08, 2026 → Nov 08, 2026
+31d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-143d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-041 - GP1 Remake G09 New ETA to warehouse: Nov 08, 2026 (was Oct 08, 2026, +31 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet Risk: At risk for the Need By date (-143 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 689. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 690 |
25-038 - - G08
East Dallas · G08 GLASS
PO 25-038-013
1 note
|
AIR |
25-038 - East Dallas - G08 - TAKA
po · 100% · PO 25-038-013
|
Nov 10, 2026 | Nov 03, 2026 |
Nov 16, 2026 → Nov 08, 2026
-8d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-4d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-038 - G08 New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet Risk: At risk for the Need By date (-4 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 690. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 694 |
25-049 -- SW7006 - SAMP
Redding Rancheria · SW 7006 COLOR SAMPLE
PO 25-049-003
|
AIR |
25-049 - Redding Rancheria - SW7006 - SAMP - TAKA
po · 100% · PO 25-049-003
|
Nov 13, 2026 | Nov 06, 2026 |
Nov 16, 2026 → Nov 08, 2026
-8d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-049 - SW7006 - SAMP New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 694. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 695 |
25-211 SW9062 color sample
25-211 SW9062 · SW9062 COLOR SAMPLE
PO 25-211-002
|
AIR |
25-211 - Deanna Davenport Elementary School -SW 9062 - TAKA
po · 100% · PO 25-211-002
|
Nov 13, 2026 | Nov 06, 2026 |
Nov 16, 2026 → Nov 08, 2026
-8d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-211 SW9062 color sample New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 695. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 696 |
26-078 -- SM10253 & 379A1455
Klein Tools · 2 COLOR SAMPLE
PO 26-078-002
|
AIR |
26-078 - Klein Tools - KAWNEER 379A1455 Permadize Champagne & SM10253 SAMP - TAKA
po · 100% · PO 26-078-002
|
Nov 06, 2026 | Oct 30, 2026 |
Nov 16, 2026 → Nov 08, 2026
-8d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-8d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-078 - SM10253 & 379A1455 New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet Risk: At risk for the Need By date (-8 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 696. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 697 |
24-075 - Infill Pack 2 Remake
DFW CTAE - · INFILL PANEL Remakes
PO NA
|
AIR |
24-075 - DFW CTAE - Infill Pack 2 Remake - TAKA
fuzzy · 100% · job 24-075 + pack IP2
|
Oct 30, 2026 | Oct 23, 2026 |
Nov 16, 2026 → Nov 08, 2026
-8d
TAKA: 2026-11-08 to DALLAS
|
At risk: Need By
-15d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 24-075 - Infill Pack 2 Remake New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment TAKA COST Risk: At risk for the Need By date (-15 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 697. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 77 · no shipment # · ETA to DALLAS | |||||||||
| 700 |
25-033 - - MP4 cover
East Montgomery - Stair 06 Handrails · Alu Cover--PC30
PO 25-033-024
|
AIR |
25-033 - East Montgomery - MP4 - TAKA
po · 100% · PO 25-033-024
|
Nov 27, 2026 | Nov 20, 2026 |
Nov 16, 2026 → Nov 15, 2026
-1d
TAKA: 2026-11-15 to DALLAS
|
On track
6d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-033 - MP4 cover New ETA to warehouse: Nov 15, 2026 (was Nov 16, 2026, -1 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: On track (6 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 700. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 703 |
26-084 - - MP2
THR Midlothian · VORTEX POST
PO 26-084-002
|
AIR |
26-084 - THR Midlothian - MP2 - TAKA
po · 100% · PO 26-084-002
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-084 - MP2 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 703. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 704 |
25-120 - - 1MP1
Clemson Veterinary(HUB BUILDING) · CUBE POST--pc35
PO 25-120-008
|
AIR |
25-120 - Clemson Veterinary - PHASE 2 - 2MP1 - TAKA
po · 100% · PO 25-120-008
|
Dec 04, 2026 | Nov 27, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
On track
13d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-120 - 1MP1 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: On track (13 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 704. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 705 |
25-120 - - 1MP2
Clemson Veterinary(HUB BUILDING) · CUBE POST--pc35
PO 25-120-004
|
AIR |
25-120 - Clemson Veterinary(HUB BUILDING)- 1MP2 - TAKA
po · 98% · PO 25-120-004 + pack 1MP2
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-120 - 1MP2 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 705. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 706 |
25-120 - - 1IP1
Clemson Veterinary(HUB BUILDING) · WM PANEL--pc35
PO 25-120-006
|
AIR |
25-120 - Clemson Veterinary(HUB BUILDING)- 1IP1 - TAKA
po · 100% · PO 25-120-006
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-120 - 1IP1 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 706. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 708 |
26-202 - - MOCK UP
TALLAHASSEE POLICE HEADQUARTERS - Florida · Mock Up --RAL5011
PO 26-202-001
|
AIR |
26-202 - TALLAHASSEE POLICE HEADQUARTERS - Florida - MOCK UP- TAKA
po · 100% · PO 26-202-001
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-202 - MOCK UP New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 708. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 709 |
25-118 - - Mock Up
NWISD - · PICKETMock Up
PO 26-099-002
|
AIR |
26-099 - NYSIF - Blade M-line - Mock Up - TAKA
po · 100% · PO 26-099-002
|
Nov 23, 2026 | Nov 16, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
On track
2d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-118 - Mock Up New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: On track (2 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 709. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 710 |
26-099 MOCK UP
- NYSIF - Blade M-line · Mock Up
PO 26-099-002
|
AIR |
26-099 - NYSIF - Blade M-line - Mock Up - TAKA
po · 100% · PO 26-099-002
|
Nov 23, 2026 | Nov 16, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
On track
2d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-099 MOCK UP New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: On track (2 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 710. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 711 |
25-136 - - IP4
Roy & Helen Hunt Library Renovation · ALU PANEL
PO 25-136-005
|
AIR |
25-136 - Roy & Helen Hunt Library Renovation - IP4 - TAKA
po · 100% · PO 25-136-005
|
Nov 19, 2026 | Nov 12, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-2d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-136 - IP4 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-2 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 711. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 712 |
25-030 -- MP3
TAMU CC · FITITNGS
PO 25-030-006
|
AIR |
25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-030 - MP3 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 712. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 713 |
25-033 -MP1 (Missing Materials)
East Montgomery - Stair 6 Remakes · FITITNGS
PO 25-033-025
|
AIR |
25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
po · 100% · PO 25-033-025
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 16, 2026 → Nov 15, 2026
-1d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-033 -MP1 (Missing Materials) New ETA to warehouse: Nov 15, 2026 (was Nov 16, 2026, -1 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 713. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 714 |
25-030 - - MP3
TAMU CC · FITITNGS
PO 25-030-006
|
AIR |
25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
|
Nov 20, 2026 | Nov 13, 2026 |
Nov 23, 2026 → Nov 15, 2026
-8d
TAKA: 2026-11-15 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-030 - MP3 New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 714. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 721 |
25-115 - - IP2
Garden City · WIRE mesh panel-- PC36
PO 25-115-008
2 notes
|
AIR |
25-115 - Garden City - IP2 - TAKA
po · 100% · PO 25-115-008
|
Nov 26, 2026 | Nov 19, 2026 |
Nov 30, 2026 → Nov 22, 2026
-8d
TAKA: 2026-11-22 to DALLAS
|
At risk: Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-115 - IP2 New ETA to warehouse: Nov 22, 2026 (was Nov 30, 2026, -8 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-22, shipment not assigned yet Risk: At risk for the Need By date (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 721. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 727 |
24-020 -- 3MP7
LHHS#2 · blade air post
PO 24-020-058
2 notes
|
AIR |
24-020 - LHHS#2 - 3MP7 - TAKA
po · 100% · PO 24-020-058
|
Dec 17, 2026 | Dec 10, 2026 |
Dec 04, 2026 → Nov 27, 2026
-7d
TAKA: 2026-11-27 to DALLAS
|
On track
17d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 24-020 - 3MP7 New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet Risk: On track (17 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 727. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 728 |
24-020 - - 3IP3
LHHS#2 · wire mesh panel
PO 24-020-059
2 notes
|
AIR |
24-020 - LHHS#2 - 3IP3 -TAKA
po · 100% · PO 24-020-059
|
Dec 17, 2026 | Dec 10, 2026 |
Dec 04, 2026 → Nov 27, 2026
-7d
TAKA: 2026-11-27 to DALLAS
|
On track
17d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 24-020 - 3IP3 New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet Risk: On track (17 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 728. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 729 |
24-040 - - - MP5 Remake
Project Meadow - LVL 2 1CL01 Cladding 10nosCL01 · CLADDING
PO 24-040-053
2 notes
|
AIR |
24-040 - Project Meadow - LVL 2 - 1CL01 Cladding 10nosCL01 - MP5 Remake - TAKA
po · 100% · PO 24-040-053
|
Nov 27, 2026 | Dec 21, 2026 |
Dec 04, 2026 → Nov 27, 2026
-7d
TAKA: 2026-11-27 to DALLAS
|
At risk: Need By
-3d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 24-040 - MP5 Remake New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days) TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet Risk: At risk for the Need By date (-3 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 729. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 78 · vessel booked · ETA to LA | |||||||||
| 736 |
25-209 - - MP1 (balance 25209-CN01--2EA )
WALTON SCHOOL · FOLD POST
PO 25-209-002
|
OCEAN |
25-209 - WALTON SCHOOL - MP1 - TAKA
po · 100% · PO 25-209-002
|
Nov 09, 2026 | Oct 30, 2026 |
Nov 10, 2026 → Nov 27, 2026
+17d
TAKA: 2026-11-13 to LA
|
At risk: LA + Need By
-18d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-209 - MP1 (balance 25209-CN01 - 2EA ) New ETA to warehouse: Nov 27, 2026 (was Nov 10, 2026, +17 days) TAKA schedule: OCEAN, ETA to LA 2026-11-13, shipment vessel booked Risk: At risk for both the LA Need By and Need By dates (-18 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 736. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| 739 |
26-089 - - MP1
SUNY Morrisville · BEACON POST-CONNECTOR
PO 26-089-002
|
OCEAN |
26-089 - SUNY Morrisville - MP1- TAKA
fuzzy · 100% · job 26-089 + pack MP1
|
Nov 27, 2026 | Nov 13, 2026 |
Oct 27, 2026 → Nov 27, 2026
+31d
TAKA: 2026-11-13 to LA
|
On track
0d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 26-089 - MP1 New ETA to warehouse: Nov 27, 2026 (was Oct 27, 2026, +31 days) TAKA schedule: OCEAN, ETA to LA 2026-11-13, shipment vessel booked Risk: On track (0 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 739. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 79 · no shipment # · ETA to LA | |||||||||
| 748 |
25-006 - -IP1
Forest Oaks · ALU PANEL--PC27
PO 25-006-001
|
OCEAN |
25-006 - Forest Oaks - IP1 - TAKA
po · 100% · PO 25-006-001
|
Dec 02, 2026 | Nov 18, 2026 |
Nov 16, 2026 → Dec 03, 2026
+17d
TAKA: 2026-11-19 to LA
|
At risk: LA + Need By
-1d slack |
Never |
Will write
Wrike comment previewTAKA ETA update for 25-006 - IP1 New ETA to warehouse: Dec 03, 2026 (was Nov 16, 2026, +17 days) TAKA schedule: OCEAN, ETA to LA 2026-11-19, shipment not assigned yet Risk: At risk for both the LA Need By and Need By dates (-1 days of slack against Need By) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 748. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
| Batch 80 · no shipment # · ETA to LA | |||||||||
| 762 |
25-049 - - MP1
Redding Rancheria · STRUC POST--MC73
PO 25-049-007
3 notes
|
OCEAN |
25-049 - Redding Rancheria - MP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 25-049 + pack MP1
|
Dec 04, 2026 |
none → Dec 22, 2026
TAKA: 2026-12-08 to LA
|
At risk: LA | Never |
Will write
Wrike comment previewTAKA ETA update for 25-049 - MP1 New ETA to warehouse: Dec 22, 2026 (first ETA from TAKA) TAKA schedule: OCEAN, ETA to LA 2026-12-08, shipment not assigned yet Risk: At risk for the LA Need By date Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 762. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
|
| 764 |
TSC-ST26039 Inventory Order - October
Inventory Order - October · Inventory Order - October
PO 003123
4 notes
|
OCEAN |
Inventory Order - October 2026 - TAKA items
po · 100% · PO 003123
|
Dec 03, 2026 → Dec 22, 2026
+19d
TAKA: 2026-12-08 to LA
|
Not assessed | Never |
Will write
Wrike comment previewTAKA ETA update for TSC-ST26039 Inventory Order - October New ETA to warehouse: Dec 22, 2026 (was Dec 03, 2026, +19 days) TAKA schedule: OCEAN, ETA to LA 2026-12-08, shipment not assigned yet Risk: Not assessed (a date is missing) Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 764. Approved by VIVA Procurement (on approval) on Nov 03, 2026. Posted by the TAKA ETA Synchronizer. |
||
Activity
- Nov 02, 2026 09:03 AM worker analysed {"lines": 678, "source": "live", "tasks": 218}
- Nov 02, 2026 09:03 AM VIVA Procurement uploaded {"filename": "2026 Delivery Schedule Template 2026-10-20.xlsx", "sha256": "0ff223cb244929602c12bbcd0636d72e7b8cfdfbe1989330cb2c60d7e1b3b740"}

Wrike comment preview