TAKA ETA Synchronizer
VIVA Procurement (lead)
← All uploads

2026 Delivery Schedule Template 2026-10-20.xlsx

Run 5 · uploaded Nov 02, 2026 09:03 AM by VIVA Procurement · sheet "Sheet1 (2)", 80 batches

ready
41will update in Wrike 141need review 448unmatched 69at risk 33 LA · 65 Need By 1waiting on TAKA 47no change

5 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.

Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 67 · SZXLAX6A088X · ETA to LA
606 26-046 - IP1 (balance part of materails)
Cobb Galleria · ALU PANEL-PPG color
PO 26-046-005
OCEAN 26-046 Cobb Galleria - IP1 - TAKA
po · 100% · PO 26-046-005
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Nov 04, 2026 +7d
TAKA: 2026-10-21 to LA
At risk: LA + Need By
-20d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-046 - IP1 (balance part of materails)
New ETA to warehouse: Nov 04, 2026 (was Oct 28, 2026, +7 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-21, shipment SZXLAX6A088X
Risk: At risk for both the LA Need By and Need By dates (-20 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 606. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 71 · SZXLAX6A132X · ETA to LA
629 26-019 - - GP1 (balance 1 case glass)
United Regional · GLASS
PO 26-019-003
OCEAN 26-019 - United Regional - GP1 -TAKA
po · 100% · PO 26-019-003
Nov 06, 2026 Oct 30, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-019 - GP1 (balance 1 case glass)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for the Need By date (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 629. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
630 26-028 MP1 (balance EP220BC)
Sapulpa High School · BEACON POST
PO 26-028-005
OCEAN 26-028 - Sapulpa High School - MP1 - TAKA
po · 100% · PO 26-028-005
Nov 06, 2026 Oct 23, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: LA + Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-028 MP1 (balance EP220BC)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for both the LA Need By and Need By dates (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 630. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
631 25-145- IP1 (balance of panels)
Kingsport Library · ALUMINUM FRAMED PANEL--PC22
PO 25-145-002
OCEAN 25-145 Kingsport Library - IP1 - TAKA
po · 100% · PO 25-145-002
Oct 30, 2026 Oct 16, 2026 Nov 04, 2026 → Nov 10, 2026 +6d
TAKA: 2026-10-27 to LA
At risk: LA + Need By
-11d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-145- IP1 (balance of panels)
New ETA to warehouse: Nov 10, 2026 (was Nov 04, 2026, +6 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: At risk for both the LA Need By and Need By dates (-11 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 631. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
632 TSC-ST26032 Color Chip Samples
Color Chip Samples · Color Chip Samples
PO VS2026-031
2 notes
  • task has no LA Need By date
  • task has no Need By date
OCEAN Taka Order - Color Chip Samples - 8-10-2026
po · 100% · PO VS2026-031
Oct 28, 2026 → Nov 10, 2026 +13d
TAKA: 2026-10-27 to LA
Not assessed Never Will write
Wrike comment preview
TAKA ETA update for TSC-ST26032 Color Chip Samples
New ETA to warehouse: Nov 10, 2026 (was Oct 28, 2026, +13 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-27, shipment SZXLAX6A132X
Risk: Not assessed (a date is missing)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 632. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 73 · SZXLAX6A235X · ETA to LA
652 26-028 - GP1
Sapulpa High School · GLASS
PO 26-028-003
OCEAN 26-028 - Sapulpa High School - GP1 - TAKA
po · 100% · PO 26-028-003
Nov 06, 2026 Oct 30, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
At risk: LA + Need By
-15d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-028 - GP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: At risk for both the LA Need By and Need By dates (-15 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 652. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
653 25-206 IP1
Newman Smith HS - Stair 4 · wire mesh panel
PO 25-206-003
OCEAN 25-206 - Newman Smith HS - Stair 4 Only - IP1-TAKA
po · 100% · PO 25-206-003
Nov 24, 2026 Nov 10, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
On track
3d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-206 IP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track (3 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 653. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
655 25-204 - MP1 (except CR121DC)
QTS DFW2-DC4 - Lobby Stair & Opening · SS316 U CAP FITTINGS
PO 25-204-003
OCEAN 25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - MP1 - TAKA
po · 100% · PO 25-204-003
Nov 24, 2026 Nov 10, 2026 Nov 27, 2026 → Nov 21, 2026 -6d
TAKA: 2026-11-07 to LA
On track
3d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-204 - MP1 (except CR121DC)
New ETA to warehouse: Nov 21, 2026 (was Nov 27, 2026, -6 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track (3 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 655. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
657 25-029 - - 2MP1
Richardson · SOLO POST
PO 25-029-007
1 note
  • task has no Need By date
OCEAN 25-029 - Richardson - 2MP1 - TAKA- PO APPROVAL
po · 100% · PO 25-029-007
Nov 09, 2026 none → Nov 21, 2026
TAKA: 2026-11-07 to LA
On track Never Will write
Wrike comment preview
TAKA ETA update for 25-029 - 2MP1
New ETA to warehouse: Nov 21, 2026 (first ETA from TAKA)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 657. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
658 25-029 - MP1
Richardson · FSR POST
PO 25-029-006
OCEAN 25-029 - Richardson - MP1 - TAKA
po · 100% · PO 25-029-006
Nov 30, 2026 Nov 09, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
On track
9d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-029 - MP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track (9 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 658. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
659 26-163 - - IP1
Publix #2111 - Lake Hills · PICKET PANEL
PO 26-163-001
OCEAN 26-163 - Publix #2111 - Lake Hills - IP1 - TAKA
po · 100% · PO 26-163-001
Dec 08, 2026 Nov 24, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
On track
17d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-163 - IP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track (17 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 659. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
660 26-163 - - MP1
Publix #2111 - Lake Hills · POST
PO 26-163-002
OCEAN 26-163 - Publix #2111 - Lake Hills - MP1 - TAKA
po · 100% · PO 26-163-002
Dec 08, 2026 Nov 24, 2026 Nov 23, 2026 → Nov 21, 2026 -2d
TAKA: 2026-11-07 to LA
On track
17d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-163 - MP1
New ETA to warehouse: Nov 21, 2026 (was Nov 23, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-07, shipment SZXLAX6A235X
Risk: On track (17 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 660. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 75 · no shipment # · ETA to DALLAS
685 25-076 - - 25076-1IP32R REMAKE
Norton ES - IP4 Remake - TAKA · 25076-1IP32R remake
PO TAKA COST
4 notes
  • task has no Need By date
  • PO number not recognised: 'TAKA COST'
  • container_dispatch 2026-10-31 differs from batch majority 2026-10-26
  • eta 2026-11-03 differs from batch majority 2026-10-30
AIR 25-076 - Norton ES - IP4 Remake - TAKA
fuzzy · 100% · job 25-076 + pack IP4
Oct 20, 2026 Nov 02, 2026 → Nov 03, 2026 +1d
TAKA: 2026-11-03 to DALLAS
Not assessed Never Will write
Wrike comment preview
TAKA ETA update for 25-076 - 25076-1IP32R REMAKE
New ETA to warehouse: Nov 03, 2026 (was Nov 02, 2026, +1 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-03, shipment not assigned yet
Risk: Not assessed (a date is missing)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 685. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
686 26-115 - MP1
Phoenix Zoo Veterinary Medical Center · CONNECTOR
PO 26-115-002
2 notes
  • container_dispatch 2026-10-31 differs from batch majority 2026-10-26
  • eta 2026-11-03 differs from batch majority 2026-10-30
AIR 26-115 - Phoenix Zoo Veterinary Medical Center MP1 - TAKA
po · 100% · PO 26-115-002
Nov 13, 2026 Nov 06, 2026 Nov 06, 2026 → Nov 03, 2026 -3d
TAKA: 2026-11-03 to DALLAS
On track
6d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-115 - MP1
New ETA to warehouse: Nov 03, 2026 (was Nov 06, 2026, -3 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-03, shipment not assigned yet
Risk: On track (6 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 686. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 76 · no shipment # · ETA to DALLAS
689 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Nov 08, 2026 +31d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-143d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-041 - GP1 Remake G09
New ETA to warehouse: Nov 08, 2026 (was Oct 08, 2026, +31 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-143 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 689. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
690 25-038 - - G08
East Dallas · G08 GLASS
PO 25-038-013
1 note
  • order_date: unrecognised date format ('101/2026')
AIR 25-038 - East Dallas - G08 - TAKA
po · 100% · PO 25-038-013
Nov 10, 2026 Nov 03, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-4d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-038 - G08
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-4 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 690. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
694 25-049 -- SW7006 - SAMP
Redding Rancheria · SW 7006 COLOR SAMPLE
PO 25-049-003
AIR 25-049 - Redding Rancheria - SW7006 - SAMP - TAKA
po · 100% · PO 25-049-003
Nov 13, 2026 Nov 06, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-049 - SW7006 - SAMP
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 694. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
695 25-211 SW9062 color sample
25-211 SW9062 · SW9062 COLOR SAMPLE
PO 25-211-002
AIR 25-211 - Deanna Davenport Elementary School -SW 9062 - TAKA
po · 100% · PO 25-211-002
Nov 13, 2026 Nov 06, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-211 SW9062 color sample
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 695. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
696 26-078 -- SM10253 & 379A1455
Klein Tools · 2 COLOR SAMPLE
PO 26-078-002
AIR 26-078 - Klein Tools - KAWNEER 379A1455 Permadize Champagne & SM10253 SAMP - TAKA
po · 100% · PO 26-078-002
Nov 06, 2026 Oct 30, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-8d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-078 - SM10253 & 379A1455
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment not assigned yet
Risk: At risk for the Need By date (-8 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 696. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
697 24-075 - Infill Pack 2 Remake
DFW CTAE - · INFILL PANEL Remakes
PO NA
AIR 24-075 - DFW CTAE - Infill Pack 2 Remake - TAKA
fuzzy · 100% · job 24-075 + pack IP2
Oct 30, 2026 Oct 23, 2026 Nov 16, 2026 → Nov 08, 2026 -8d
TAKA: 2026-11-08 to DALLAS
At risk: Need By
-15d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-075 - Infill Pack 2 Remake
New ETA to warehouse: Nov 08, 2026 (was Nov 16, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-08, shipment TAKA COST
Risk: At risk for the Need By date (-15 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 697. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 77 · no shipment # · ETA to DALLAS
700 25-033 - - MP4 cover
East Montgomery - Stair 06 Handrails · Alu Cover--PC30
PO 25-033-024
AIR 25-033 - East Montgomery - MP4 - TAKA
po · 100% · PO 25-033-024
Nov 27, 2026 Nov 20, 2026 Nov 16, 2026 → Nov 15, 2026 -1d
TAKA: 2026-11-15 to DALLAS
On track
6d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-033 - MP4 cover
New ETA to warehouse: Nov 15, 2026 (was Nov 16, 2026, -1 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: On track (6 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 700. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
703 26-084 - - MP2
THR Midlothian · VORTEX POST
PO 26-084-002
AIR 26-084 - THR Midlothian - MP2 - TAKA
po · 100% · PO 26-084-002
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-084 - MP2
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 703. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
704 25-120 - - 1MP1
Clemson Veterinary(HUB BUILDING) · CUBE POST--pc35
PO 25-120-008
AIR 25-120 - Clemson Veterinary - PHASE 2 - 2MP1 - TAKA
po · 100% · PO 25-120-008
Dec 04, 2026 Nov 27, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
13d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-120 - 1MP1
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: On track (13 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 704. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
705 25-120 - - 1MP2
Clemson Veterinary(HUB BUILDING) · CUBE POST--pc35
PO 25-120-004
AIR 25-120 - Clemson Veterinary(HUB BUILDING)- 1MP2 - TAKA
po · 98% · PO 25-120-004 + pack 1MP2
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-120 - 1MP2
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 705. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
706 25-120 - - 1IP1
Clemson Veterinary(HUB BUILDING) · WM PANEL--pc35
PO 25-120-006
AIR 25-120 - Clemson Veterinary(HUB BUILDING)- 1IP1 - TAKA
po · 100% · PO 25-120-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-120 - 1IP1
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 706. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
708 26-202 - - MOCK UP
TALLAHASSEE POLICE HEADQUARTERS - Florida · Mock Up --RAL5011
PO 26-202-001
AIR 26-202 - TALLAHASSEE POLICE HEADQUARTERS - Florida - MOCK UP- TAKA
po · 100% · PO 26-202-001
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-202 - MOCK UP
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 708. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
709 25-118 - - Mock Up
NWISD - · PICKETMock Up
PO 26-099-002
AIR 26-099 - NYSIF - Blade M-line - Mock Up - TAKA
po · 100% · PO 26-099-002
Nov 23, 2026 Nov 16, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
2d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-118 - Mock Up
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: On track (2 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 709. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
710 26-099 MOCK UP
- NYSIF - Blade M-line · Mock Up
PO 26-099-002
AIR 26-099 - NYSIF - Blade M-line - Mock Up - TAKA
po · 100% · PO 26-099-002
Nov 23, 2026 Nov 16, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
On track
2d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-099 MOCK UP
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: On track (2 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 710. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
711 25-136 - - IP4
Roy & Helen Hunt Library Renovation · ALU PANEL
PO 25-136-005
AIR 25-136 - Roy & Helen Hunt Library Renovation - IP4 - TAKA
po · 100% · PO 25-136-005
Nov 19, 2026 Nov 12, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-2d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-136 - IP4
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-2 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 711. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
712 25-030 -- MP3
TAMU CC · FITITNGS
PO 25-030-006
AIR 25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-030 - MP3
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 712. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
713 25-033 -MP1 (Missing Materials)
East Montgomery - Stair 6 Remakes · FITITNGS
PO 25-033-025
AIR 25-033 - East Montgomery - Stair 6 Remakes MP1 (Missing Materials) - TAKA
po · 100% · PO 25-033-025
Nov 20, 2026 Nov 13, 2026 Nov 16, 2026 → Nov 15, 2026 -1d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-033 -MP1 (Missing Materials)
New ETA to warehouse: Nov 15, 2026 (was Nov 16, 2026, -1 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 713. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
714 25-030 - - MP3
TAMU CC · FITITNGS
PO 25-030-006
AIR 25-030 - TAMU CC - MP3 - TAKA
po · 100% · PO 25-030-006
Nov 20, 2026 Nov 13, 2026 Nov 23, 2026 → Nov 15, 2026 -8d
TAKA: 2026-11-15 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-030 - MP3
New ETA to warehouse: Nov 15, 2026 (was Nov 23, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-15, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 714. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
721 25-115 - - IP2
Garden City · WIRE mesh panel-- PC36
PO 25-115-008
2 notes
  • container_dispatch 2026-11-20 differs from batch majority 2026-11-14
  • eta 2026-11-22 differs from batch majority 2026-11-15
AIR 25-115 - Garden City - IP2 - TAKA
po · 100% · PO 25-115-008
Nov 26, 2026 Nov 19, 2026 Nov 30, 2026 → Nov 22, 2026 -8d
TAKA: 2026-11-22 to DALLAS
At risk: Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-115 - IP2
New ETA to warehouse: Nov 22, 2026 (was Nov 30, 2026, -8 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-22, shipment not assigned yet
Risk: At risk for the Need By date (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 721. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
727 24-020 -- 3MP7
LHHS#2 · blade air post
PO 24-020-058
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR 24-020 - LHHS#2 - 3MP7 - TAKA
po · 100% · PO 24-020-058
Dec 17, 2026 Dec 10, 2026 Dec 04, 2026 → Nov 27, 2026 -7d
TAKA: 2026-11-27 to DALLAS
On track
17d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-020 - 3MP7
New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet
Risk: On track (17 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 727. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
728 24-020 - - 3IP3
LHHS#2 · wire mesh panel
PO 24-020-059
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR 24-020 - LHHS#2 - 3IP3 -TAKA
po · 100% · PO 24-020-059
Dec 17, 2026 Dec 10, 2026 Dec 04, 2026 → Nov 27, 2026 -7d
TAKA: 2026-11-27 to DALLAS
On track
17d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-020 - 3IP3
New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet
Risk: On track (17 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 728. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
729 24-040 - - - MP5 Remake
Project Meadow - LVL 2 1CL01 Cladding 10nosCL01 · CLADDING
PO 24-040-053
2 notes
  • container_dispatch 2026-11-23 differs from batch majority 2026-11-14
  • eta 2026-11-27 differs from batch majority 2026-11-15
AIR 24-040 - Project Meadow - LVL 2 - 1CL01 Cladding 10nosCL01 - MP5 Remake - TAKA
po · 100% · PO 24-040-053
Nov 27, 2026 Dec 21, 2026 Dec 04, 2026 → Nov 27, 2026 -7d
TAKA: 2026-11-27 to DALLAS
At risk: Need By
-3d slack
Never Will write
Wrike comment preview
TAKA ETA update for 24-040 - MP5 Remake
New ETA to warehouse: Nov 27, 2026 (was Dec 04, 2026, -7 days)
TAKA schedule: AIR, ETA to DALLAS 2026-11-27, shipment not assigned yet
Risk: At risk for the Need By date (-3 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 729. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 78 · vessel booked · ETA to LA
736 25-209 - - MP1 (balance 25209-CN01--2EA )
WALTON SCHOOL · FOLD POST
PO 25-209-002
OCEAN 25-209 - WALTON SCHOOL - MP1 - TAKA
po · 100% · PO 25-209-002
Nov 09, 2026 Oct 30, 2026 Nov 10, 2026 → Nov 27, 2026 +17d
TAKA: 2026-11-13 to LA
At risk: LA + Need By
-18d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-209 - MP1 (balance 25209-CN01 - 2EA )
New ETA to warehouse: Nov 27, 2026 (was Nov 10, 2026, +17 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-13, shipment vessel booked
Risk: At risk for both the LA Need By and Need By dates (-18 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 736. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
739 26-089 - - MP1
SUNY Morrisville · BEACON POST-CONNECTOR
PO 26-089-002
OCEAN 26-089 - SUNY Morrisville - MP1- TAKA
fuzzy · 100% · job 26-089 + pack MP1
Nov 27, 2026 Nov 13, 2026 Oct 27, 2026 → Nov 27, 2026 +31d
TAKA: 2026-11-13 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 26-089 - MP1
New ETA to warehouse: Nov 27, 2026 (was Oct 27, 2026, +31 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-13, shipment vessel booked
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 739. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 79 · no shipment # · ETA to LA
748 25-006 - -IP1
Forest Oaks · ALU PANEL--PC27
PO 25-006-001
OCEAN 25-006 - Forest Oaks - IP1 - TAKA
po · 100% · PO 25-006-001
Dec 02, 2026 Nov 18, 2026 Nov 16, 2026 → Dec 03, 2026 +17d
TAKA: 2026-11-19 to LA
At risk: LA + Need By
-1d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-006 - IP1
New ETA to warehouse: Dec 03, 2026 (was Nov 16, 2026, +17 days)
TAKA schedule: OCEAN, ETA to LA 2026-11-19, shipment not assigned yet
Risk: At risk for both the LA Need By and Need By dates (-1 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 748. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
Batch 80 · no shipment # · ETA to LA
762 25-049 - - MP1
Redding Rancheria · STRUC POST--MC73
PO 25-049-007
3 notes
  • task has no Need By date
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN 25-049 - Redding Rancheria - MP1 - TAKA- PO APPROVAL
fuzzy · 90% · job 25-049 + pack MP1
Dec 04, 2026 none → Dec 22, 2026
TAKA: 2026-12-08 to LA
At risk: LA Never Will write
Wrike comment preview
TAKA ETA update for 25-049 - MP1
New ETA to warehouse: Dec 22, 2026 (first ETA from TAKA)
TAKA schedule: OCEAN, ETA to LA 2026-12-08, shipment not assigned yet
Risk: At risk for the LA Need By date
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 762. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
764 TSC-ST26039 Inventory Order - October
Inventory Order - October · Inventory Order - October
PO 003123
4 notes
  • task has no LA Need By date
  • task has no Need By date
  • container_dispatch 2026-11-24 differs from batch majority 2026-11-12
  • eta 2026-12-08 differs from batch majority 2026-11-26
OCEAN Inventory Order - October 2026 - TAKA items
po · 100% · PO 003123
Dec 03, 2026 → Dec 22, 2026 +19d
TAKA: 2026-12-08 to LA
Not assessed Never Will write
Wrike comment preview
TAKA ETA update for TSC-ST26039 Inventory Order - October
New ETA to warehouse: Dec 22, 2026 (was Dec 03, 2026, +19 days)
TAKA schedule: OCEAN, ETA to LA 2026-12-08, shipment not assigned yet
Risk: Not assessed (a date is missing)
Source: 2026 Delivery Schedule Template 2026-10-20.xlsx, row 764. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.

Activity

41 lines approved for Wrike (ETA field), with 41 comments · dry run. 589 still need a look and will stay in the exception queue.

Link to a Wrike task