TAKA ETA Synchronizer
VIVA Procurement (lead)
← All uploads

2026 Delivery Schedule Template 2026-08-26.xlsx

Run 3 · uploaded Oct 30, 2026 10:58 AM by VIVA Procurement · sheet "Sheet1 (2)", 11 batches

ready
4will update in Wrike 22need review 60unmatched 9at risk 7 LA · 8 Need By 1waiting on TAKA 2no change

422 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.

Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 63 · no shipment # · ETA to LA
572 25-155 MP1
Del Norte · BLADE POST
PO NA
OCEAN 25-155 - Del Norte - MP1 -TAKA
fuzzy · 100% · job 25-155 + pack MP1
Nov 02, 2026 Oct 19, 2026 Oct 28, 2026 → Nov 02, 2026 +5d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-155 MP1
New ETA to warehouse: Nov 02, 2026 (was Oct 28, 2026, +5 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 572. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
573 25-155 - IP1
Del Norte - · PERFORATED PANEL
PO NA
OCEAN 25-155 - Del Norte - IP1 - TAKA
fuzzy · 100% · job 25-155 + pack IP1
Nov 02, 2026 Oct 19, 2026 Nov 04, 2026 → Nov 02, 2026 -2d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-155 - IP1
New ETA to warehouse: Nov 02, 2026 (was Nov 04, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 573. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
574 25-051 - - IP1
Ball State Performing Arts Center
PO NA
OCEAN 25-051 - Ball State Performing Arts Center - IP1 - TAKA
fuzzy · 100% · job 25-051 + pack IP1
Nov 02, 2026 Oct 19, 2026 Oct 12, 2026 → Nov 02, 2026 +21d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-051 - IP1
New ETA to warehouse: Nov 02, 2026 (was Oct 12, 2026, +21 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 574. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
575 25-145- IP1
Kingsport Library
PO NA
1 note
  • eta 2026-10-16 differs from batch majority 2026-10-19
OCEAN 25-145 Kingsport Library - IP1 - TAKA
fuzzy · 100% · job 25-145 + pack IP1
Oct 30, 2026 Oct 16, 2026 Nov 04, 2026 → Oct 30, 2026 -5d
TAKA: 2026-10-16 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-145- IP1
New ETA to warehouse: Oct 30, 2026 (was Nov 04, 2026, -5 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-16, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 575. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.

Activity

4 lines approved for Wrike (ETA field), with 4 comments · dry run. 82 still need a look and will stay in the exception queue.

Link to a Wrike task