TAKA ETA Synchronizer
VIVA Procurement (lead)
← All uploads

2026 Delivery Schedule Template 2026-08-26.xlsx

Run 3 · uploaded Oct 30, 2026 10:58 AM by VIVA Procurement · sheet "Sheet1 (2)", 11 batches

ready
4will update in Wrike 22need review 60unmatched 9at risk 7 LA · 8 Need By 1waiting on TAKA 2no change

422 rows hidden in Excel were skipped (TAKA hides shipped batches). Unhide them in the workbook and upload again to include them.

Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 58 · Flight booked · ETA to DALLAS
518 25-041 - - GP1 Remake G09
Jackson Walker · BEND GLASS
PO NA
1 note
  • new ETA Sep 06, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
AIR 25-041 - Jackson Walker - GP1 Remake- TAKA
fuzzy · 100% · job 25-041 + pack GP1
1 candidate
Jun 24, 2026 Jun 17, 2026 Oct 08, 2026 → Sep 06, 2026 -32d
TAKA: 2026-09-06 to DALLAS
At risk: Need By
-80d slack
Never Needs review
Batch 60 · vessel booked · ETA to LA
544 24-075 - IP1
DFW CTAE AREA C4 · 12mm LASER CUT PANEL - PP11--color as sample
PO 24-075-027
5 notes
  • task has no Need By date
  • new ETA Oct 01, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
  • metal_ready: unrecognised date format ('COLOR HAVE NOT CONFIRMED')
  • vessel_loading: unrecognised date format ('COLOR HAVE NOT CONFIRMED')
  • container_dispatch: unrecognised date format ('COLOR HAVE NOT CONFIRMED')
OCEAN 24-075 - DFW CTAE - AREA C4 (BRIDGES) - IP1 - TAKA- PO APPROVAL
po · 100% · PO 24-075-027
Sep 10, 2026 none → Oct 01, 2026
TAKA: 2026-09-17 to LA
At risk: LA Never Needs review
Batch 61 · no shipment # · ETA to LA
555 25-125 -- GP1
CACC Aviation Hangar · GLASS
PO 25-125-005
1 note
  • new ETA Oct 08, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-125 - CACC Aviation Hangar - GP1 -TAKA
po · 100% · PO 25-125-005
Oct 06, 2026 Sep 22, 2026 Oct 22, 2026 → Oct 08, 2026 -14d
TAKA: 2026-09-24 to LA
At risk: LA + Need By
-2d slack
Never Needs review
Batch 62 · no shipment # · ETA to LA
557 26-046 - MP1
Cobb Galleria · FRAME POST-PPG color
PO NA
2 notes
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
  • container_dispatch 2026-09-28 differs from batch majority 2026-09-30
OCEAN 26-046 Cobb Galleria - MP1 - TAKA
fuzzy · 100% · job 26-046 + pack MP1
2 candidates
Oct 14, 2026 Oct 15, 2026 Oct 28, 2026 → Oct 26, 2026 -2d
TAKA: 2026-10-12 to LA
At risk: Need By
-12d slack
Never Needs review
558 26-046 - IP1
Cobb Galleria · ALU PANEL-PPG color
PO NA
1 note
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 26-046 Cobb Galleria - IP1 - TAKA
fuzzy · 100% · job 26-046 + pack IP1
2 candidates
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Oct 26, 2026 -2d
TAKA: 2026-10-12 to LA
At risk: LA + Need By
-11d slack
Never Needs review
559 24-212 1MP1
CISD - Crowley High School - Texas - Phase 2, Arena B&C · CIRCA -FSR POST
PO NA
2 notes
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
  • container_dispatch 2026-09-28 differs from batch majority 2026-09-30
OCEAN 24-212 - CISD - Crowley High School - Texas - Phase 2, Arena B&C - 1MP1 - TAKA
fuzzy · 100% · job 24-212 + pack 1MP1
2 candidates
Oct 15, 2026 Oct 01, 2026 Oct 28, 2026 → Oct 26, 2026 -2d
TAKA: 2026-10-12 to LA
At risk: LA + Need By
-11d slack
Never Needs review
564 25-096 - 3MP1
Cicero North HS Pool · SS316 VIEW BUTTON
PO NA
1 note
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-096 - Cicero North HS Pool - 3MP1 - TAKA
fuzzy · 100% · job 25-096 + pack 3MP1
2 candidates
Oct 20, 2026 Sep 30, 2026 Oct 22, 2026 → Oct 26, 2026 +4d
TAKA: 2026-10-12 to LA
At risk: LA + Need By
-6d slack
Never Needs review
565 25-096 3GP1
Cicero North HS Pool · 21.52pvb glass
PO NA
1 note
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 25-096 - Cicero North HS Pool - 3GP1 - TAKA
fuzzy · 100% · job 25-096 + pack 3GP1
2 candidates
Oct 22, 2026 Oct 08, 2026 Oct 22, 2026 → Oct 26, 2026 +4d
TAKA: 2026-10-12 to LA
At risk: LA + Need By
-4d slack
Never Needs review
566 26-062 - - MP2
TAMU COD · CUBE POST
PO NA
1 note
  • new ETA Oct 26, 2026 is already in the past; the shipment has probably arrived or this is an old schedule
OCEAN 26-062 - TAMU COD- MP2- TAKA
fuzzy · 100% · job 26-062 + pack MP2
1 candidate
Oct 21, 2026 Oct 07, 2026 Oct 22, 2026 → Oct 26, 2026 +4d
TAKA: 2026-10-12 to LA
At risk: LA + Need By
-5d slack
Never Needs review

Activity

4 lines approved for Wrike (ETA field), with 4 comments · dry run. 82 still need a look and will stay in the exception queue.

Link to a Wrike task