TAKA ETA Synchronizer
VIVA Procurement (lead)
← All uploads

2026 Delivery Schedule Template 2026-08-26.xlsx

Run 2 · uploaded Oct 28, 2026 03:25 PM by VIVA Procurement · sheet "Sheet1 (2)", 63 batches

ready
5will update in Wrike 81need review 418unmatched 14at risk 10 LA · 13 Need By 1waiting on TAKA 6no change
Row Schedule line Mode Wrike task Need By LA Need By Prior ETA → New ETA Risk PM last notified Decision
Batch 63 · no shipment # · ETA to LA
571 25-155 - MP2
Del Norte · CONNECTOR
PO NA
OCEAN 25-155 - Del Norte - MP2 - TAKA
fuzzy · 100% · job 25-155 + pack MP2
Nov 02, 2026 Oct 19, 2026 Oct 22, 2026 → Nov 02, 2026 +11d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-155 - MP2
New ETA to warehouse: Nov 02, 2026 (was Oct 22, 2026, +11 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 571. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
572 25-155 MP1
Del Norte · BLADE POST
PO NA
OCEAN 25-155 - Del Norte - MP1 -TAKA
fuzzy · 100% · job 25-155 + pack MP1
Nov 02, 2026 Oct 19, 2026 Oct 28, 2026 → Nov 02, 2026 +5d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-155 MP1
New ETA to warehouse: Nov 02, 2026 (was Oct 28, 2026, +5 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 572. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
573 25-155 - IP1
Del Norte - · PERFORATED PANEL
PO NA
OCEAN 25-155 - Del Norte - IP1 - TAKA
fuzzy · 100% · job 25-155 + pack IP1
Nov 02, 2026 Oct 19, 2026 Nov 04, 2026 → Nov 02, 2026 -2d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-155 - IP1
New ETA to warehouse: Nov 02, 2026 (was Nov 04, 2026, -2 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 573. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
574 25-051 - - IP1
Ball State Performing Arts Center
PO NA
OCEAN 25-051 - Ball State Performing Arts Center - IP1 - TAKA
fuzzy · 100% · job 25-051 + pack IP1
Nov 02, 2026 Oct 19, 2026 Oct 12, 2026 → Nov 02, 2026 +21d
TAKA: 2026-10-19 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-051 - IP1
New ETA to warehouse: Nov 02, 2026 (was Oct 12, 2026, +21 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-19, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 574. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.
575 25-145- IP1
Kingsport Library
PO NA
1 note
  • eta 2026-10-16 differs from batch majority 2026-10-19
OCEAN 25-145 Kingsport Library - IP1 - TAKA
fuzzy · 100% · job 25-145 + pack IP1
Oct 30, 2026 Oct 16, 2026 Nov 04, 2026 → Oct 30, 2026 -5d
TAKA: 2026-10-16 to LA
On track
0d slack
Never Will write
Wrike comment preview
TAKA ETA update for 25-145- IP1
New ETA to warehouse: Oct 30, 2026 (was Nov 04, 2026, -5 days)
TAKA schedule: OCEAN, ETA to LA 2026-10-16, shipment not assigned yet
Risk: On track (0 days of slack against Need By)
Source: 2026 Delivery Schedule Template 2026-08-26.xlsx, row 575. Approved by VIVA Procurement (on approval) on Nov 03, 2026.
Posted by the TAKA ETA Synchronizer.

Activity

5 lines approved for Wrike (ETA field), with 5 comments · dry run. 499 still need a look and will stay in the exception queue.

Link to a Wrike task