Wrike taskStageModePMNeed ByETA to WHDays lateLA Need byContainerPO valueRisk (Wrike)PM last notified
26-127 - Gainesville PD - Mock Up - TAKA Quote and approval
PM Approval Needed
AIR MO Oct 08, 2026 Oct 22, 2026 +14 Sep 30, 2026 $249 3. At Risk
DELAYED
Never
25-212 - Celina ES 7- BAA MP AML - TAKA At TAKA
In Works / AT vendor
OCEAN MO Dec 25, 2026 Dec 28, 2026 +3 Dec 11, 2026 $737 3. At Risk Never
25-215 Celina ES 8 - BAA MP AML - TAKA At TAKA
In Works / AT vendor
OCEAN MO Dec 25, 2026 Dec 28, 2026 +3 Dec 11, 2026 $731 3. At Risk Never
25-050 - Cheshire Elementary School - IP1 & IP2 Remakes - TAKA Received / QC
Partial Material RCVD
AIR MO Nov 06, 2026 Nov 02, 2026 -4 Oct 30, 2026 SZXCHI6A004Y 1. On Track
DELAYED
Never
25-051 - Ball State Performing Arts Center - IP1 - TAKA Received / QC
QC complete
OCEAN MO Nov 02, 2026 Oct 12, 2026 -21 Oct 19, 2026 SZXCH6A002Y $18,624 1. On Track
DELAYED
Never
26-109 - TSA - TAKA At TAKA
In Works / AT vendor
OCEAN MO Dec 22, 2026 Nov 17, 2026 $52,798 3. At Risk Never
25-050 - Cheshire Elementary School - IP1 & IP2 Remakes - TAKA- PO APPROVAL Quote and approval
RFQ SENT
AIR MO Oct 30, 2026 1. On Track Never
25-051 - Ball State Performing Arts Center- EXPEDITED (POST)- MP1 - TAKA- PO APPROVAL Quote and approval
RISHAB APPROVAL
AIR MO Sep 29, 2026 $5,240 1. On Track Never
26-076 - Prairie SS Center - Blade WM- Mock Up - TAKA- PO APPROVAL Quote and approval
QUOTE ISSUE
AIR MO Oct 16, 2026 $302 1. On Track Never