| Wrike task | Stage | Mode | PM | Need By | ETA to WH | Days late | LA Need by | Container | PO value | Risk (Wrike) | PM last notified |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 26-127 - Gainesville PD - Mock Up - TAKA | Quote and approval PM Approval Needed |
AIR | MO | Oct 08, 2026 | Oct 22, 2026 | +14 | Sep 30, 2026 | $249 | 3. At Risk DELAYED |
Never | |
| 25-212 - Celina ES 7- BAA MP AML - TAKA | At TAKA In Works / AT vendor |
OCEAN | MO | Dec 25, 2026 | Dec 28, 2026 | +3 | Dec 11, 2026 | $737 | 3. At Risk | Never | |
| 25-215 Celina ES 8 - BAA MP AML - TAKA | At TAKA In Works / AT vendor |
OCEAN | MO | Dec 25, 2026 | Dec 28, 2026 | +3 | Dec 11, 2026 | $731 | 3. At Risk | Never | |
| 25-050 - Cheshire Elementary School - IP1 & IP2 Remakes - TAKA | Received / QC Partial Material RCVD |
AIR | MO | Nov 06, 2026 | Nov 02, 2026 | -4 | Oct 30, 2026 | SZXCHI6A004Y | 1. On Track DELAYED |
Never | |
| 25-051 - Ball State Performing Arts Center - IP1 - TAKA | Received / QC QC complete |
OCEAN | MO | Nov 02, 2026 | Oct 12, 2026 | -21 | Oct 19, 2026 | SZXCH6A002Y | $18,624 | 1. On Track DELAYED |
Never |
| 26-109 - TSA - TAKA | At TAKA In Works / AT vendor |
OCEAN | MO | Dec 22, 2026 | Nov 17, 2026 | $52,798 | 3. At Risk | Never | |||
| 25-050 - Cheshire Elementary School - IP1 & IP2 Remakes - TAKA- PO APPROVAL | Quote and approval RFQ SENT |
AIR | MO | Oct 30, 2026 | 1. On Track | Never | |||||
| 25-051 - Ball State Performing Arts Center- EXPEDITED (POST)- MP1 - TAKA- PO APPROVAL | Quote and approval RISHAB APPROVAL |
AIR | MO | Sep 29, 2026 | $5,240 | 1. On Track | Never | ||||
| 26-076 - Prairie SS Center - Blade WM- Mock Up - TAKA- PO APPROVAL | Quote and approval QUOTE ISSUE |
AIR | MO | Oct 16, 2026 | $302 | 1. On Track | Never |