Open vendor = TAKA tasks, Wrike data read Nov 03, 2026 02:05 PM. Sorted by days late, then ETA.
| Wrike task | Stage | Mode | PM | Need By | ETA to WH | Days late | LA Need by | Container | PO value | Risk (Wrike) | PM last notified |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 25-062 - RDNI - IP3- TAKA | Shipping In Transit |
AIR | Coleby | Nov 06, 2026 | Nov 16, 2026 | +10 | Oct 30, 2026 | $106 | 3. At Risk DELAYED |
Never | |
| 26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - GP1 - TAKA | Shipping In Transit |
OCEAN | Coleby | Nov 27, 2026 | Dec 03, 2026 | +6 | Nov 13, 2026 | SZXLAX6N057X | $6,230 | 3. At Risk DELAYED |
Never |
| 25-006 - Forest Oaks - MP1 - TAKA | Received / QC Partial Material RCVD |
AIR | Coleby | Nov 04, 2026 | Nov 09, 2026 | +5 | Oct 22, 2026 | $2,579 | 3. At Risk DELAYED |
Never | |
| 25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - GP1 - TAKA | Shipping In Transit |
AIR | Coleby | Nov 23, 2026 | Nov 27, 2026 | +4 | Nov 09, 2026 | SZXLAX6A335X | $10,975 | 3. At Risk | Never |
| 25-118 - NWISD - PICKET MOCK-UP #2 - TAKA | At TAKA In Works / AT vendor |
AIR | Coleby | Nov 20, 2026 | Nov 23, 2026 | +3 | Nov 13, 2026 | $280 | 3. At Risk DELAYED |
Never | |
| 26-088 - Eastern Hills - AML - TAKA | Shipping In Transit |
OCEAN | Coleby | Nov 20, 2026 | Nov 23, 2026 | +3 | Nov 06, 2026 | SZXLAX6A235X | $2,905 | 2. Potential Risk DELAYED |
Never |
| 25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - MP1 - TAKA | Shipping In Transit |
OCEAN | Coleby | Nov 24, 2026 | Nov 27, 2026 | +3 | Nov 10, 2026 | SZXLAX6A335X | $2,946 | 3. At Risk DELAYED |
Never |
| 25-072 - Celina Govt Center - Phase 1 Roof and Floor Opening - 1MP1 - TAKA | Shipping In Transit |
OCEAN | Coleby | Dec 01, 2026 | Nov 27, 2026 | -4 | Nov 17, 2026 | SZXLAX6A335X | $4,911 | 1. On Track DELAYED |
Never |
| 25-118 - NWISD - PHASE 2 AREA A and B - 2MP1 ( EXPEDITE PORTION) -TAKA | At TAKA In Works / AT vendor |
AIR | Coleby | Dec 10, 2026 | Dec 04, 2026 | -6 | Dec 03, 2026 | $358 | 1. On Track DELAYED |
Never | |
| 25-072 - Celina Govt Center - PH1 Roof & Floor Opening - 1GP1 - HG | At TAKA In Works / AT vendor |
VENDOR DELIVERY | Coleby | Dec 01, 2026 | Nov 17, 2026 | -14 | Nov 26, 2026 | $5,904 | 1. On Track DELAYED |
Never | |
| 25-118 - NWISD - PHASE 1 - METAL 1MP2 - TAKA | At TAKA In Works / AT vendor |
OCEAN | Coleby | Dec 04, 2026 | Nov 20, 2026 | -14 | Nov 20, 2026 | $22,158 | 1. On Track | Never | |
| 25-006 - Forest Oaks - IP1 - TAKA | Shipping In Transit |
OCEAN | Coleby | Dec 02, 2026 | Nov 16, 2026 | -16 | Nov 18, 2026 | SZXLAX6N057X | $11,176 | 1. On Track DELAYED |
Never |
| 25-118 - NWISD - PHASE 2 AREA A and B - 2MP1 - TAKA | At TAKA In Works / AT vendor |
OCEAN | Coleby | Dec 25, 2026 | Oct 28, 2026 | -58 | Dec 11, 2026 | $2,671 | 3. At Risk DELAYED |
Never | |
| 25-142 - QTS DFW2 DC3 - MP1 - TAKA | At TAKA Order RCVD |
AIR | Coleby | Aug 21, 2026 | Aug 12, 2026 | DELAYED |
Never | ||||
| 25-118 - NWISD - SAMP - TAKA | Received / QC Partial Material RCVD |
AIR | Coleby | Nov 02, 2026 | Oct 09, 2026 | SZXCHI6A004Y | $506 | 3. At Risk DELAYED |
Never | ||
| 26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - MP1 - TAKA | Shipping In Transit |
OCEAN | Coleby | Nov 27, 2026 | Nov 27, 2026 | 0 | Nov 13, 2026 | $6,950 | 3. At Risk DELAYED |
Never | |
| 25-204 - QTS DFW2-DC4 - BR106VA SS316 - TAKA- PO APPROVAL | Quote and approval RFQ SENT |
OCEAN | Coleby | Nov 20, 2026 | 1. On Track | Never | |||||
| 26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - GP1 - TAKA- PO APPROVAL | Quote and approval Ankit Approval |
OCEAN | Coleby | Nov 13, 2026 | $6,230 | 1. On Track DELAYED |
Never | ||||
| 26-071 - Purdue ASB - Perf FOLD - Mock Up - TAKA | Exceptions Order on Hold |
AIR | Coleby | Nov 27, 2026 | Nov 20, 2026 | 1. On Track | Never | ||||
| 26-071 - Purdue ASB - Perf FOLD - Mock Up - TAKA- PO APPROVALII | Quote and approval RFQ SENT |
AIR | Coleby | Nov 20, 2026 | 1. On Track | Never |