Wrike taskStageModePMNeed ByETA to WHDays lateLA Need byContainerPO valueRisk (Wrike)PM last notified
25-062 - RDNI - IP3- TAKA Shipping
In Transit
AIR Coleby Nov 06, 2026 Nov 16, 2026 +10 Oct 30, 2026 $106 3. At Risk
DELAYED
Never
26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - GP1 - TAKA Shipping
In Transit
OCEAN Coleby Nov 27, 2026 Dec 03, 2026 +6 Nov 13, 2026 SZXLAX6N057X $6,230 3. At Risk
DELAYED
Never
25-006 - Forest Oaks - MP1 - TAKA Received / QC
Partial Material RCVD
AIR Coleby Nov 04, 2026 Nov 09, 2026 +5 Oct 22, 2026 $2,579 3. At Risk
DELAYED
Never
25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - GP1 - TAKA Shipping
In Transit
AIR Coleby Nov 23, 2026 Nov 27, 2026 +4 Nov 09, 2026 SZXLAX6A335X $10,975 3. At Risk Never
25-118 - NWISD - PICKET MOCK-UP #2 - TAKA At TAKA
In Works / AT vendor
AIR Coleby Nov 20, 2026 Nov 23, 2026 +3 Nov 13, 2026 $280 3. At Risk
DELAYED
Never
26-088 - Eastern Hills - AML - TAKA Shipping
In Transit
OCEAN Coleby Nov 20, 2026 Nov 23, 2026 +3 Nov 06, 2026 SZXLAX6A235X $2,905 2. Potential Risk
DELAYED
Never
25-204 - QTS DFW2-DC4 - Lobby Stair & Opening - MP1 - TAKA Shipping
In Transit
OCEAN Coleby Nov 24, 2026 Nov 27, 2026 +3 Nov 10, 2026 SZXLAX6A335X $2,946 3. At Risk
DELAYED
Never
25-072 - Celina Govt Center - Phase 1 Roof and Floor Opening - 1MP1 - TAKA Shipping
In Transit
OCEAN Coleby Dec 01, 2026 Nov 27, 2026 -4 Nov 17, 2026 SZXLAX6A335X $4,911 1. On Track
DELAYED
Never
25-118 - NWISD - PHASE 2 AREA A and B - 2MP1 ( EXPEDITE PORTION) -TAKA At TAKA
In Works / AT vendor
AIR Coleby Dec 10, 2026 Dec 04, 2026 -6 Dec 03, 2026 $358 1. On Track
DELAYED
Never
25-072 - Celina Govt Center - PH1 Roof & Floor Opening - 1GP1 - HG At TAKA
In Works / AT vendor
VENDOR DELIVERY Coleby Dec 01, 2026 Nov 17, 2026 -14 Nov 26, 2026 $5,904 1. On Track
DELAYED
Never
25-118 - NWISD - PHASE 1 - METAL 1MP2 - TAKA At TAKA
In Works / AT vendor
OCEAN Coleby Dec 04, 2026 Nov 20, 2026 -14 Nov 20, 2026 $22,158 1. On Track Never
25-006 - Forest Oaks - IP1 - TAKA Shipping
In Transit
OCEAN Coleby Dec 02, 2026 Nov 16, 2026 -16 Nov 18, 2026 SZXLAX6N057X $11,176 1. On Track
DELAYED
Never
25-118 - NWISD - PHASE 2 AREA A and B - 2MP1 - TAKA At TAKA
In Works / AT vendor
OCEAN Coleby Dec 25, 2026 Oct 28, 2026 -58 Dec 11, 2026 $2,671 3. At Risk
DELAYED
Never
25-142 - QTS DFW2 DC3 - MP1 - TAKA At TAKA
Order RCVD
AIR Coleby Aug 21, 2026 Aug 12, 2026
DELAYED
Never
25-118 - NWISD - SAMP - TAKA Received / QC
Partial Material RCVD
AIR Coleby Nov 02, 2026 Oct 09, 2026 SZXCHI6A004Y $506 3. At Risk
DELAYED
Never
26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - MP1 - TAKA Shipping
In Transit
OCEAN Coleby Nov 27, 2026 Nov 27, 2026 0 Nov 13, 2026 $6,950 3. At Risk
DELAYED
Never
25-204 - QTS DFW2-DC4 - BR106VA SS316 - TAKA- PO APPROVAL Quote and approval
RFQ SENT
OCEAN Coleby Nov 20, 2026 1. On Track Never
26-047 - Lab 4.0 Core & Shell - Stair 2 w/ Smoke Baffle - GP1 - TAKA- PO APPROVAL Quote and approval
Ankit Approval
OCEAN Coleby Nov 13, 2026 $6,230 1. On Track
DELAYED
Never
26-071 - Purdue ASB - Perf FOLD - Mock Up - TAKA Exceptions
Order on Hold
AIR Coleby Nov 27, 2026 Nov 20, 2026 1. On Track Never
26-071 - Purdue ASB - Perf FOLD - Mock Up - TAKA- PO APPROVALII Quote and approval
RFQ SENT
AIR Coleby Nov 20, 2026 1. On Track Never