PM: Andres Diaz (18)
Open vendor = TAKA tasks, Wrike data read Nov 03, 2026 02:35 PM. Sorted by days late, then ETA.
| Wrike task | Stage | Mode | PM | Need By | ETA to WH | Days late | LA Need by | Container | PO value | Risk (Wrike) | PM last notified |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 25-114 - Crowley - IP1 - TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Nov 13, 2026 | Nov 27, 2026 | +14 | Nov 20, 2026 | SZXLAX6A335X | $4,708 | 3. At Risk DELAYED |
Never |
| 25-075 - UM Gem Factory - IP2 remakes - TAKA | Received / QC QC complete |
AIR | Andres Diaz | Oct 23, 2026 | Nov 02, 2026 | +10 | Oct 16, 2026 | SZXCHI6A004Y | $1,069 | 3. At Risk DELAYED |
Never |
| 25-115 - Garden City - IP2 - TAKA | At TAKA In Works / AT vendor |
AIR | Andres Diaz | Nov 26, 2026 | Nov 30, 2026 | +4 | Nov 19, 2026 | $1,261 | 3. At Risk DELAYED |
Never | |
| 25-096 - Cicero North HS Pool - 3MP1 - TAKA | Received / QC QC complete |
OCEAN | Andres Diaz | Oct 20, 2026 | Oct 22, 2026 | +2 | Sep 30, 2026 | SZXLAX69368X | $1,317 | 3. At Risk DELAYED |
Never |
| 26-089 - SUNY Morrisville - IP1 - TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Dec 01, 2026 | Dec 03, 2026 | +2 | Nov 17, 2026 | SZXLAX6N057X | $8,864 | 3. At Risk | Never |
| 25-048 - Dillard Rd - GP1 Remake - TAKA | At TAKA In Works / AT vendor |
AIR | Andres Diaz | Dec 01, 2026 | Nov 23, 2026 | -8 | Nov 24, 2026 | 1. On Track | Never | ||
| 25-115 - Garden City - P02 - MP1 Remake -TAKA | Received / QC QC complete |
AIR | Andres Diaz | Nov 13, 2026 | Nov 02, 2026 | -11 | Nov 06, 2026 | SZXCHI6A004Y | $70 | 1. On Track DELAYED |
Never |
| 25-114 - Crowley - MP1 - TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Nov 20, 2026 | Nov 09, 2026 | -11 | Nov 06, 2026 | SZXLAX6A132X | $2,622 | 3. At Risk DELAYED |
Never |
| 26-030 - Saratoga - GP1 - TAKA | At TAKA In Works / AT vendor |
OCEAN | Andres Diaz | Dec 25, 2026 | Dec 10, 2026 | -15 | Dec 11, 2026 | $566 | 2. Potential Risk DELAYED |
Never | |
| 26-089 - SUNY Morrisville - MP1- TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Nov 27, 2026 | Oct 27, 2026 | -31 | Nov 13, 2026 | SZXLAX6A335X | $6,458 | 3. At Risk DELAYED |
Never |
| 25-096 - Cicero North HS Pool - 3GP1 - TAKA | Received / QC Partial Material RCVD |
OCEAN | Andres Diaz | Oct 22, 2026 | Oct 22, 2026 | 0 | Oct 08, 2026 | SZXLAX69368X | $2,774 | 3. At Risk DELAYED |
Never |
| 25-181 - First & Market - MP1 - TAKA | Shipping In Transit |
OCEAN | Andres Diaz | Nov 09, 2026 | Nov 09, 2026 | 0 | Oct 30, 2026 | SZXLAX6A132X | $5,839 | 1. On Track DELAYED |
Never |
| 25-048 - Dillard Rd - GP1 Remake - TAKA- PO APPROVAL | Quote and approval RFQ SENT |
AIR | Andres Diaz | Nov 24, 2026 | 1. On Track | Never | |||||
| 25-149 - New Albany - MP1 - TAKA- PO APPROVAL | Quote and approval Hussein Approval |
Andres Diaz | $8,980 | Never | |||||||
| 25-149 - New Albany - remakes - IP2 - TAKA | At TAKA In Works / AT vendor |
AIR | Andres Diaz | Dec 22, 2026 | Dec 15, 2026 | $548 | 1. On Track DELAYED |
Never | |||
| 25-149 - New Albany - remakes - MP2 - TAKA | At TAKA In Works / AT vendor |
AIR | Andres Diaz | Dec 18, 2026 | Dec 11, 2026 | $363 | 1. On Track DELAYED |
Never | |||
| 25-182 - CSH - IP2 - TAKA | At TAKA In Works / AT vendor |
AIR | Andres Diaz | Dec 11, 2026 | Dec 04, 2026 | $78 | 1. On Track DELAYED |
Never | |||
| 26-089 - SUNY Morrisville - MP1- TAKA- PO APPROVAL | Quote and approval Ankit Approval |
OCEAN | Andres Diaz | Nov 13, 2026 | $6,458 | 1. On Track | Never |